A construction method for demolishing buildings on existing track operating section
A technology with existing rails and construction methods, applied in building construction, construction, building maintenance, etc., can solve the problems of long construction period and difficult construction of buildings, and achieve the goal of ensuring construction efficiency, facilitating installation and dismantling, and ensuring construction safety Effect
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0030] The present invention relates to a construction method for demolishing buildings on an existing track operation section, comprising the following steps: erecting a safety isolation protection structure in the track section of the existing track to separate the track section and the operation area, so as to ensure that the running of the train and the demolition construction will not be interrupted. Influence each other, and implement the requirements of safe operation and closed isolation of the track.
[0031] The safety isolation and protection structures are located on both sides and above the track area or only on both sides of the track area. When the building to be demolished crosses the track area, the safety isolation and protection structures on both sides and above the track area are used to protect the track area. When the buildings to be demolished are located on both sides of the track area and do not cross the track area, the safety isolation protection str...
Embodiment 2
[0037] The invention relates to a construction method for demolishing a building in an existing track operation section. The building to be demolished is a station, and the station includes a station main structure located on one side of the track area, a platform structure located on the track area, and a station located in the track area. The other side of the bridge is attached to the stairs, and the platform structure includes platform plates on both sides of the track area and a spanning structure above the track area.
[0038] The removal sequence is:
[0039] Step a, use the skylight points where the track is out of service at night to complete the erection of the safety isolation protection structure, and then erect the lighting glass protection net before removing the attached stairs of the overpass to protect the lighting glass on the platform wall, and finally use the shearing equipment. The auxiliary stairs of the overpass are removed, and the shearing equipment ad...
PUM
Login to View More Abstract
Description
Claims
Application Information
Login to View More - R&D
- Intellectual Property
- Life Sciences
- Materials
- Tech Scout
- Unparalleled Data Quality
- Higher Quality Content
- 60% Fewer Hallucinations
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2025 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com