Giant-span underground cave depot reserved double-rock-pillar support eight-part excavation construction method

A construction method and cavern technology, applied in underground chambers, earthwork drilling, wellbore lining, etc., can solve the problems of no technical standard construction technology, no successful case projects, and high economic costs, so as to achieve spacious construction space and ensure surrounding rock stability and high operating efficiency

Pending Publication Date: 2021-06-04
CHINA RAILWAY TUNNEL GROUP CO LTD +2
View PDF5 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

However, due to the small size of each block, after each excavation part is excavated, the temporary support is followed up in time to stabilize the deformation of the surrounding rock. After all the excavation parts are excavated and supported, the temporary support is removed, which can effectively Control the deformation of the surrounding rock to ensure the stability of the surrounding rock and construction safety, but the project progress is slow and the economic cost is high. How to achieve the best compromise between

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Giant-span underground cave depot reserved double-rock-pillar support eight-part excavation construction method
  • Giant-span underground cave depot reserved double-rock-pillar support eight-part excavation construction method

Examples

Experimental program
Comparison scheme
Effect test

Example Embodiment

[0028] According to a giant across underground cave, a double-rock column supports eight excavation construction methods for use in hard surrounding rock formation spans more than 70m, but less than 75m giant across underground calendering project, and the surrounding rock belongs to II Or level III, ie [BQ] is between 400 ~ 550; applicable cave section: straight wall archless free arch flat section, the height of the side wall does not exceed 10m, the height does not exceed 10m; requires the ground water level The cave floor is below the floor.

[0029] In the construction, the opening of the opening surface is partitioned. figure 1 with figure 2 As shown, the opening surface of the cave is vertically up and down, and the portion of the arch line is from the upper part of the construction area, and the following part is the lower part of the construction area;

[0030] In the upper part of the construction zone, the central region is set to the first portion 1, and the portion of...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

The invention discloses a reserved double-rock-pillar support eight-part excavation construction method for a huge-span underground cave depot, which comprises the following steps: 1, dividing an excavation surface of the cave depot into an upper part and a lower part which are independent from each other in the vertical direction, taking the part above an arch camber line as an upper part construction area, and taking the part below the arch camber line as a lower part construction area; 2, excavating the first part in a full-section mode till the front end wall is reached; 3, excavating transverse channels towards the left side and the right side at the front end wall of the first part till the second part area is reached; 4, in the two second part areas on the left side and the right side, excavating pilot tunnels backwards in the reverse direction from the tunnel face till the tunnels go out of the tunnel. 5, excavating the third part at the bottom till the front end wall is reached; 6, excavating fourth parts on the left side and the right side in a staggered mode till the front end wall; and 7, excavating the fifth part till the position of the front end wall. According to the construction method, original surrounding rock masses are fully utilized to replace manual materials to serve as temporary supports of the cave depot, and the material cost is saved.

Description

technical field [0001] The invention belongs to the technical field, and in particular relates to an excavation construction method for eight sections supported by double rock pillars reserved for a giant-span underground cavern. Background technique [0002] For the long-span underground cavern project in hard rock formation, when the span does not exceed 40m, the relatively mature half-section method and step method can be selected according to factors such as surrounding rock formation conditions, cavern span size, mechanical equipment technical level, and surrounding environment. , Double-side wall pilot pit method, single rock pillar support divisional excavation method and other construction methods, these methods are relatively mature at present, and have formed technical standards and specifications. Firstly, according to the geological survey results, determine the RQD value of the stratum, and determine the grade of the surrounding rock, and then preliminarily dete...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
IPC IPC(8): E21D9/00E21D11/00E21D11/10
CPCE21D9/00E21D11/006E21D11/10
Inventor 杨朝帅刘永胜卓越姚士磊林春刚邵阳熊炎林种玉配杨效广安博金星亮代昱昊尚伟
Owner CHINA RAILWAY TUNNEL GROUP CO LTD
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products