Concrete precast beam winter heat preservation construction method
A construction method and concrete technology, which is applied in the direction of manufacturing tools, pretreatment control, clay preparation equipment, etc., can solve problems that have not been found, and achieve the effects of ensuring construction progress, avoiding manual long-term operation, and steam balance
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0024] The present invention is described in further detail below by embodiment, and embodiment is only used for illustrating the present invention, does not limit the scope of the present invention.
[0025] Project Overview:
[0026] Sichuan Shuangjiangkou Hydropower Station is located in Malkang County and Jinchuan County, Sichuan Province, with an altitude of more than 2300m. It is winter from late October to early March of the following year. During this period, the lowest temperature during concrete pouring reaches above -15°C, and the temperature difference between day and night is large.
[0027] Shuangjiangkou 2# Diversion Tunnel Keryingou 2# Bridge has a total length of about 117m and is designed to consist of 8 pieces of 35m long T-shaped prestressed beams and 16 pieces of 16m hollow slab beams. Among them, the T-shaped beam is 2.5m high, the bottom of the beam body is 0.5m wide, the top of the wing plate is prefabricated with a wide width of 2m, 25m of wet joints a...