Large-diameter vertical shaft excavation support construction method
A construction method and large-diameter technology, applied in shaft equipment, well-sinking, earth-moving drilling and mining, etc., can solve the problems of inconsistent shaft size and design size, low construction efficiency, collapse, etc., to improve dimensional accuracy and strength, improve construction Efficiency, the effect of avoiding collapse
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0043] In order to make the object, technical solution and advantages of the present invention clearer, the present invention will be further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described here are only used to explain the present invention, not to limit the present invention.
[0044] The embodiment of the present invention provides a large-diameter shaft excavation support construction method, combined with the attached figure 1 to attach Figure 22 shown, including the following steps.
[0045] S1, construction on the top floor, first excavate a trench along the direction of the exit of the hall, after the excavation of the trench is completed, lay ramps at both ends of the trench, and then excavate the remaining parts divided into 6 areas in order dig.
[0046] In this embodiment, the construction height of the top floor is 5 meters, which is the first floor.
[00...