System and method for safety construction of industrial control network of energy station
An industrial control network and station technology, applied in the field of energy station industrial control network security construction, can solve problems such as difficulty, lack of a standardized construction plan, and a small number of industrial control network security systems, reducing labor and time investment.
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0086] XXX power plant
[0087] The first attribute parameter:
[0088] Control area (safety I area): including 2 field-level distributed control systems (DCS systems), 1 auxiliary control system
[0089] Non-controlled area (Security II area): including a field-level information monitoring system
[0090] Management information area (Security III area): includes 1 management information system
[0091] The second attribute parameter:
[0092] Station type: thermal power plant
[0093] Installed capacity: 200MW
[0094] Construction plan calculation process:
[0095] 1. According to the second attribute parameter, if the type of the station is a thermal power plant, and the installed capacity is 200MW>100MW, it is determined that the station is a standard construction method of a thermal power plant. Therefore, the collection scope of the construction plan is the control area of the power plant (safety area I) , non-control area (Security II area) and management inform...
Embodiment 2
[0099] XXX power plant
[0100] The first attribute parameter:
[0101] Control area (safety I area): including a field-level distributed control system (DCS system)
[0102] Non-controlled area (Security II area): including a field-level information monitoring system
[0103] Management information area (Security III area): includes 1 management information system
[0104] The second attribute parameter:
[0105] Station type: thermal power plant
[0106] Installed capacity: 80MW
[0107] Construction plan calculation process:
[0108] 1. According to the second attribute parameter, if the station type is a thermal power plant and the installed capacity is 80MW Figure 6 shown;
[0109] 2. According to the first attribute parameter, the large management information area (security III area) contains 1 management information system and requires 1 data collector, so only 1 data collector is required.
[0110] 3. Therefore, the detailed deployment of the construction plan c...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com