Construction method of heavy-load-resistant acid-proof terrace

A construction method and floor technology, applied in the direction of chemical instruments and methods, inorganic non-surface-active cleaning compositions, floors, etc., can solve the problems that the flatness of the floor layer cannot be fully guaranteed, and the construction method is cumbersome, etc., and achieve good durability. The effect of heavy load and heavy acid resistance, simple construction and short construction process

Pending Publication Date: 2022-05-13
FENGFA GRP CO LTD
1 Cites 0 Cited by

AI-Extracted Technical Summary

Problems solved by technology

[0004] Although the above-mentioned floor has the advantages of being resistant to heavy loads and heavy acids, it still has som...
View more

Method used

Wherein, heavy-duty anti-acid floor construction method construction is simple, construction procedure is shorter, and the floor after construction has good heavy-duty and heavy-acid-resistant ability, and flatness is high; By adopting base surface cleaning, Basic surface cleaning, foundation surface grinding, manual leveling, vibration scraping, fine-leveling treatment, troweling treatment, polishing treatment and other steps can fully ensure the flatness of the floor, and the foundation surface and floor The surface has been maintained to further increase its lifespan.
Wherein, heavy-duty anti-acid floor construction method construction is simple, construction procedure is shorter, and the floor after construction has good heavy-duty and heavy-acid-resistant ability, and flatness is high; By adopting basic surface cleaning, Basic surface cleaning, foun...
View more

Abstract

The invention discloses a construction method of a heavy-load-resistant acid-proof terrace. According to the technical scheme, the construction method is characterized by comprising the following steps that S1, the surface of a foundation is cleaned, wherein cement laitance, old paint and adhered garbage sundries on the surface of the foundation of the terrace to be laid are removed; s2, cleaning the surface of the foundation, wherein oil stains on the surface of the foundation on which the terrace is to be laid are removed; s3, the surface of the base is ground flat; s4, the surface of the foundation is maintained, specifically, the surface of the foundation is maintained; s5, paving a heavy-load-resistant acid-proof floor; s6, manual flattening: performing manual primary flattening under the control of an infrared gradienter; s7, vibration slicking is conducted, specifically, vibration slicking is conducted through a laser leveling machine; s8, fine leveling treatment, wherein fine leveling is conducted through a scraping bar or a rolling bar; s9, troweling treatment is conducted, specifically, a troweling machine is used for conducting flexible pressing and troweling with a reel; s10, carrying out polishing treatment; the construction method of the heavy-load-resistant acid-proof terrace is simple in construction and short in construction procedure, and the constructed terrace has good heavy load resistance and heavy acid resistance and is high in flatness.

Application Domain

Organic non-surface-active detergent compositionsInorganic non-surface-active detergent compositions +1

Technology Topic

ChemistryPolishing +9

Image

  • Construction method of heavy-load-resistant acid-proof terrace

Examples

  • Experimental program(3)

Example Embodiment

[0030] Example 1
[0031] like figure 1 , the present embodiment provides a heavy-duty anti-acid floor construction method, comprising the following steps:
[0032] S1. Foundation surface cleaning: remove cement laitance, old paint and adhered garbage on the foundation surface to be laid;
[0033] S2. Foundation surface cleaning: remove oil stains on the foundation surface to be laid;
[0034] S3. Foundation surface grinding: use dust-free sweeper, large vacuum cleaner and grinding machine to clean, dry and smooth the foundation surface;
[0035] S4. Foundation surface maintenance: maintenance of the foundation surface;
[0036] S5. Laying of heavy-duty anti-acid floor: First lay cement mortar layer, resin glass fiber reinforced plastic layer, quartz sand layer and self-leveling layer on the foundation surface in sequence;
[0037] S6. Manual leveling: under the control of the infrared level, perform manual leveling for the first time;
[0038] S7. Vibration scraping: use laser leveling machine to vibrate and scrape;
[0039] S8. Fine-leveling treatment: use scraper or roller for fine-leveling;
[0040] S9. Smoothing treatment: smoothing with gentle pressure on the tape of the trowel;
[0041] S10. Polishing treatment: Overall polishing with driving type grinder;
[0042] S11. Curing solution curing: Spray curing solution for curing.
[0043] Wherein, in said S2, when removing the oil stain on the foundation surface of the floor to be laid, the oil stain cleaning agent is used for cleaning, and the oil stain cleaning agent includes the following mass components: 20 parts of trisodium phosphate, 15 parts of sodium tripolyphosphate , 15 parts of sodium carbonate, 12 parts of sodium metasilicate, 2 parts of sodium hydroxide, and 8 parts of sodium citrate.
[0044] Wherein, in said S3, the allowable void on the foundation surface is 2 mm, and the water content is below 8%.
[0045] Wherein, in the above S4, when the surface of the foundation is maintained, the perchlorethylene resin plastic solution is sprayed on the surface of the foundation with a spray gun, and the curing temperature is controlled at 28° C., and the curing time is 5 days.
[0046] Wherein, in the S5, when laying the heavy-duty acid-proof floor, the thickness of the cement mortar layer is 4cm, the thickness of the resin glass fiber reinforced plastic layer is 1cm, the thickness of the quartz sand layer is 1cm, and the thickness of the self-leveling layer is 1cm. .
[0047] Wherein, in the above S10, when the driving type grinder is overall polishing, the flatness of the control surface is 2-3mm.
[0048] Wherein, during the smoothing treatment of the S9, glass beads are sprayed on the surface first, and then smoothed with soft pressure with a trowel.
[0049] Wherein, in the S11, when the curing liquid is sprayed for curing, the curing liquid includes the following mass percentage components: paraffin wax 65%, water glass 35%.
[0050] Among them, the heavy-duty acid-resistant floor construction method is simple in construction, and the construction process is short, and the floor after construction has good heavy-load and heavy-acid resistance, and high flatness; by using foundation surface cleaning, foundation surface cleaning , foundation surface grinding, artificial flattening, vibration scraping, fine-leveling treatment, troweling treatment, polishing treatment and other steps can fully ensure the flatness of the floor, and both the foundation surface and the floor surface are carried out during the production of the floor With the maintenance, its lifespan is further improved.

Example Embodiment

[0051] Example 2
[0052] like figure 1 , the present embodiment provides a heavy-duty anti-acid floor construction method, comprising the following steps:
[0053] S1. Foundation surface cleaning: remove cement laitance, old paint and adhered garbage on the foundation surface to be laid;
[0054] S2. Foundation surface cleaning: remove oil stains on the foundation surface to be laid;
[0055] S3. Foundation surface grinding: use dust-free sweeper, large vacuum cleaner and grinding machine to clean, dry and smooth the foundation surface;
[0056] S4. Foundation surface maintenance: maintenance of the foundation surface;
[0057] S5. Laying of heavy-duty anti-acid floor: First lay cement mortar layer, resin glass fiber reinforced plastic layer, quartz sand layer and self-leveling layer on the foundation surface in sequence;
[0058] S6. Manual leveling: under the control of the infrared level, perform manual leveling for the first time;
[0059] S7. Vibration scraping: use laser leveling machine to vibrate and scrape;
[0060] S8. Fine-leveling treatment: use scraper or roller for fine-leveling;
[0061] S9. Smoothing treatment: smoothing with gentle pressure on the tape of the trowel;
[0062] S10. Polishing treatment: Overall polishing with driving type grinder;
[0063] S11. Curing solution curing: Spray curing solution for curing.
[0064]Wherein, in said S2, when removing the oil stain on the foundation surface of the floor to be laid, the oil stain cleaning agent is used for cleaning, and the oil stain cleaning agent includes the following mass components: 20 parts of trisodium phosphate, 15 parts of sodium tripolyphosphate , 15 parts of sodium carbonate, 12 parts of sodium metasilicate, 2 parts of sodium hydroxide, and 8 parts of sodium citrate.
[0065] Wherein, in said S3, the allowable gap on the foundation surface is 2.5 mm, and the water content is below 8%.
[0066] Wherein, in the above S4, when the surface of the foundation is maintained, the perchlorethylene resin plastic solution is sprayed on the surface of the foundation with a spray gun, and the curing temperature is controlled at 30° C., and the curing time is 5 days.
[0067] Wherein, in the S5, when laying the heavy-duty acid-proof floor, the thickness of the cement mortar layer is 6cm, the thickness of the resin glass fiber reinforced plastic layer is 2cm, the thickness of the quartz sand layer is 1cm, and the thickness of the self-leveling layer is 2cm .
[0068] Wherein, in the above S10, when the driving type grinder is integrally polished, the flatness of the control surface is 2 mm.
[0069] Wherein, during the smoothing treatment of the S9, glass beads are sprayed on the surface first, and then smoothed with soft pressure with a trowel.
[0070] Wherein, in the S11, when the curing liquid is sprayed for curing, the curing liquid includes the following mass percentage components: paraffin wax 65%, water glass 35%.
[0071] Among them, the heavy-duty acid-resistant floor construction method is simple in construction, and the construction process is short, and the floor after construction has good heavy-load and heavy-acid resistance, and high flatness; by using foundation surface cleaning, foundation surface cleaning , foundation surface grinding, artificial flattening, vibration scraping, fine-leveling treatment, troweling treatment, polishing treatment and other steps can fully ensure the flatness of the floor, and both the foundation surface and the floor surface are carried out during the production of the floor With the maintenance, its lifespan is further improved.

Example Embodiment

[0072] Example 3
[0073] like figure 1 , the present embodiment provides a heavy-duty anti-acid floor construction method, comprising the following steps:
[0074] S1. Foundation surface cleaning: remove cement laitance, old paint and adhered garbage on the foundation surface to be laid;
[0075] S2. Foundation surface cleaning: remove oil stains on the foundation surface to be laid;
[0076] S3. Foundation surface grinding: use dust-free sweeper, large vacuum cleaner and grinding machine to clean, dry and smooth the foundation surface;
[0077] S4. Foundation surface maintenance: maintenance of the foundation surface;
[0078] S5. Laying of heavy-duty anti-acid floor: First lay cement mortar layer, resin glass fiber reinforced plastic layer, quartz sand layer and self-leveling layer on the foundation surface in sequence;
[0079] S6. Manual leveling: under the control of the infrared level, perform manual leveling for the first time;
[0080] S7. Vibration scraping: use laser leveling machine to vibrate and scrape;
[0081] S8. Fine-leveling treatment: use scraper or roller for fine-leveling;
[0082] S9. Smoothing treatment: smoothing with gentle pressure on the tape of the trowel;
[0083] S10. Polishing treatment: Overall polishing with driving type grinder;
[0084] S11. Curing solution curing: Spray curing solution for curing.
[0085] Wherein, in said S2, when removing the oil stain on the foundation surface of the floor to be laid, the oil stain cleaning agent is used for cleaning, and the oil stain cleaning agent includes the following mass components: 20 parts of trisodium phosphate, 15 parts of sodium tripolyphosphate , 15 parts of sodium carbonate, 12 parts of sodium metasilicate, 2 parts of sodium hydroxide, and 8 parts of sodium citrate.
[0086] Wherein, in said S3, the allowable gap on the foundation surface is 2.3 mm, and the moisture content is below 8%.
[0087] Wherein, in the above S4, when the surface of the foundation is maintained, the perchlorethylene resin plastic solution is sprayed on the surface of the foundation with a spray gun, and the curing temperature is controlled at 29° C., and the curing time is 5 days.
[0088] Wherein, in the S5, when laying the heavy-duty acid-proof floor, the thickness of the cement mortar layer is 5cm, the thickness of the resin glass fiber reinforced plastic layer is 1.5cm, the thickness of the quartz sand layer is 0.8cm, and the thickness of the self-leveling layer It is 1.5cm.
[0089] Wherein, in the above S10, when the driving type grinder is overall polishing, the flatness of the control surface is 2.5mm.
[0090] Wherein, during the smoothing treatment of the S9, glass beads are sprayed on the surface first, and then smoothed with soft pressure with a trowel.
[0091] Wherein, in the S11, when the curing liquid is sprayed for curing, the curing liquid includes the following mass percentage components: paraffin wax 65%, water glass 35%.
[0092] Among them, the heavy-duty acid-resistant floor construction method is simple in construction, and the construction process is short, and the floor after construction has good heavy-load and heavy-acid resistance, and high flatness; by using foundation surface cleaning, foundation surface cleaning , foundation surface grinding, artificial flattening, vibration scraping, fine-leveling treatment, troweling treatment, polishing treatment and other steps can fully ensure the flatness of the floor, and both the foundation surface and the floor surface are carried out during the production of the floor With the maintenance, its lifespan is further improved.

PUM

PropertyMeasurementUnit
Thickness5.0cm
Thickness1.5cm
Thickness0.8cm

Description & Claims & Application Information

We can also present the details of the Description, Claims and Application information to help users get a comprehensive understanding of the technical details of the patent, such as background art, summary of invention, brief description of drawings, description of embodiments, and other original content. On the other hand, users can also determine the specific scope of protection of the technology through the list of claims; as well as understand the changes in the life cycle of the technology with the presentation of the patent timeline. Login to view more.

Similar technology patents

Underwater drawing tablet

InactiveUS7264477B1simple constructionimpervious
Owner:HAGAN MARK LLOYD

Developing device and image forming device equipped with same

ActiveUS20060198655A1stable sealing capabilitysimple construction
Owner:KYOCERA DOCUMENT SOLUTIONS INC

Classification and recommendation of technical efficacy words

  • Simple construction

Methods and apparatus for searching backup data based on content and attributes

ActiveUS20050166082A1eliminate need , cost and overheadsimple construction
Owner:T W STORAGE

Electrically driven brake booster

InactiveUS20020158510A1reduce weightsimple construction
Owner:BOSCH AUTOMOTIVE SYST CORP

Pivoting hatch cover assembly

InactiveUS6095365Asimple constructionlow clearance
Owner:HEIL CO THE

Plastic lid for a can

InactiveUS20050092751A1simple constructioncost reduction
Owner:BRASILATA S A EMBALAGENS METALICAS
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products