Unlock instant, AI-driven research and patent intelligence for your innovation.

Tunnel reinforced concrete two-lining explosion-control dismantling charging structure and construction method

A technology for reinforced concrete and tunnels, which is applied in the field of charge structures and constructions for the controlled blasting demolition of reinforced concrete secondary linings in tunnels. The effect of ground impact

Pending Publication Date: 2022-05-13
四川路航建设工程有限责任公司
View PDF0 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

When damage occurs and needs to be dismantled, demolition is relatively easy because there is no steel skeleton in the plain concrete secondary lining structure
When the reinforced concrete secondary lining is removed, the difficulty of the operation will be greatly increased due to the involvement of the steel skeleton in the secondary lining concrete structure. When the traditional weak loosening blasting is used, the surrounding primary support and surrounding rock will be greatly disturbed, which will easily cause secondary disasters; When the broken head is used for demolition, the work efficiency is low and the safety risk is large

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Tunnel reinforced concrete two-lining explosion-control dismantling charging structure and construction method
  • Tunnel reinforced concrete two-lining explosion-control dismantling charging structure and construction method
  • Tunnel reinforced concrete two-lining explosion-control dismantling charging structure and construction method

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0029] The following will be combined with Figure 1-Figure 5 The present invention is described in detail, and the technical solutions in the embodiments of the present invention are clearly and completely described. Apparently, the described embodiments are only some of the embodiments of the present invention, not all of them. Based on the embodiments of the present invention, all other embodiments obtained by persons of ordinary skill in the art without making creative efforts belong to the protection scope of the present invention.

[0030] The present invention hereby provides a kind of tunnel reinforced concrete second liner controlled explosion demolition charging structure, such as Figure 1-Figure 5 As shown, it can be implemented in the following way: divide the demolition into sections based on the construction joint position of the second lining concrete, arrange the arch waist blasting area 1 symmetrically at the arch waists on both sides of the second lining, an...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention provides a tunnel reinforced concrete secondary lining explosion control dismantling charging structure and a construction method, and is characterized in that blasting sections are symmetrically arranged on haunches and side walls on two sides of a secondary lining, five vertical sections are arranged on the haunches, and drill holes in each section are parallel and inclined upwards; wherein the side wall is provided with four flat sections, and drill holes in each section are parallel and incline towards the outer side of the tunnel. Concrete with the thickness of 3 cm is reserved at the bottom of the drill hole to serve as a protective layer, and a discontinuous interval charging structure is adopted in the hole. And the detonating sequence is that the haunch blast holes on the two sides are detonated firstly, then the side wall blast holes on the two sides are detonated after delaying for half second, and the adjacent blast holes in the longitudinal direction of the tunnel are delayed for 100 ms. The principle is as follows: concrete in a blasting area is easily fragmented by adopting dense blast holes and an interval charging structure, and the concrete fragments are stripped from reinforcing steel bars to form a weak area; and the vault secondary lining concrete in the non-explosion section overcomes the supporting force of the reinforcing steel bars in the weak area of the haunch to fall down, and drives the arch wall in the non-explosion section to flex down around the weak area of the side wall until the secondary lining concrete falls to the ground. The method is suitable for dismantling the tunnel reinforced concrete secondary lining.

Description

technical field [0001] The invention belongs to a method for dismantling a secondary lining structure in the technical field of tunnel construction, and specifically relates to a controlled blasting dismantling charge structure and a construction method for a reinforced concrete secondary lining of a tunnel. Background technique [0002] During the construction and operation of the tunnel, due to engineering quality defects or poor geology, the secondary lining concrete may not be able to resist the pressure of the surrounding rock, resulting in deformation, cracking, or even damage. Commonly used tunnel secondary lining concrete includes plain concrete and reinforced concrete. When it needs to be dismantled and replaced due to damage, because there is no steel skeleton in the plain concrete secondary lining structure, it is relatively easy to dismantle. When the reinforced concrete secondary lining is removed, the difficulty of the operation will be greatly increased due t...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Applications(China)
IPC IPC(8): F42D1/10F42D3/04F42D1/05E21D9/00
CPCF42D1/10F42D3/04F42D1/05E21D9/006
Inventor 张丹张剑宁管连永刘复红黄鹏陆凌王翎鉴
Owner 四川路航建设工程有限责任公司