Construction method for semi-circular pile of covered and excavated station

A construction method, semi-circular technology, applied to artificial islands, sheet pile walls, water conservancy projects, etc., can solve problems such as difficulty in ensuring project quality and troublesome construction of semi-circular piles, and achieve easy demolition, reduced labor input, and reduced cost input Effect

Pending Publication Date: 2022-07-05
CHINA RAILWAY NO 3 GRP CO LTD +2
View PDF8 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0004] The purpose of the present invention is to provide a construction method for the semicircle pile of the cover excavation station, so as to solve the problem that the construction of the semicircle pile in the prior art is troublesome and difficult to ensure the quality of the project

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Construction method for semi-circular pile of covered and excavated station
  • Construction method for semi-circular pile of covered and excavated station

Examples

Experimental program
Comparison scheme
Effect test

Embodiment 1

[0049] In this embodiment, the construction method of the semi-circular piles at the cover and excavation station adopts the following steps: setting out the pile positions on the enclosure piles, carrying out drilling construction on the ground 5 according to the pile positions to form the pile holes; preparing the steel cage 1, in the In the reinforcing bar cage 1, part of the reinforcing bars protrude radially to form a semicircular bar cage 2 with a circular arc profile; a bamboo plywood 3 is set, and the bamboo plywood 3 is connected to the semicircular bar cage 2; It is inserted in the pile hole; the concrete 7 is poured into the pile hole and solidified; the crown beam is set with a retaining wall, and earthwork is excavated; the bamboo plywood 3 is removed to obtain a semi-circular pile.

[0050] The semicircular rib cage 2 is welded with positioning ribs 4 , and the positioning ribs 4 are arranged in two and disposed on opposite sides respectively so as to extend to th...

Embodiment 2

[0054] In this embodiment, the construction method for the semi-circular piles of the cover and excavation station includes the following steps: stake out the enclosure piles, and drill holes on the ground 5 according to the pile positions to form pile holes; In the reinforcing bar cage 1, part of the reinforcing bars protrude radially to form a semicircular bar cage 2 with a circular arc profile; a bamboo plywood 3 is set, and the bamboo plywood 3 is connected to the semicircular bar cage 2; It is inserted in the pile hole; the concrete 7 is poured into the pile hole and solidified; the crown beam is set with a retaining wall, and earthwork is excavated; the bamboo plywood 3 is removed to obtain a semi-circular pile.

[0055] The semicircular rib cage 2 is welded with positioning ribs 4 . The positioning ribs 4 are arranged in two and are respectively arranged on opposite sides so as to extend to the ground 5 and coincide with the pile holes on the ground 5 . The bamboo plywo...

Embodiment 3

[0060] In this embodiment, the construction method for the semi-circular piles of the cover and excavation station includes the following steps: stake out the enclosure piles, carry out drilling construction on the ground 5 according to the pile positions, and form pile holes; prepare steel cages 1, In the reinforcing bar cage 1, part of the reinforcing bars protrude radially to form a semicircular bar cage 2 with a circular arc profile; a bamboo plywood 3 is set, and the bamboo plywood 3 is connected to the semicircular bar cage 2; the reinforcing bar cage 1 is lowered, It is inserted in the pile hole; the concrete 7 is poured into the pile hole and solidified; the crown beam is set with a retaining wall, and earthwork is excavated; the bamboo plywood 3 is removed to obtain a semi-circular pile.

[0061] The semi-circular rib cage 2 is welded with positioning ribs 4 . The positioning ribs 4 are arranged in two and are respectively arranged on opposite sides so as to be able to...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention discloses a construction method for a semi-circular pile of a covered and excavated station. The construction method for covering and digging the semicircular piles of the station comprises the following steps that pile position lofting is conducted on fender posts, and positioning holes are formed in the ground according to the structures of the fender posts; a reinforcement cage is prepared, and in the reinforcement cage, part of reinforcing steel bars protrude in the radial direction to form a semicircular reinforcement cage with an arc-shaped outline; bamboo plywood is arranged, and the bamboo plywood is connected to the semicircular rib cage; a reinforcement cage is put down to be inserted into the pile hole; concrete is poured into the reinforcement cage and solidified; arranging a top beam and a retaining wall, and excavating earth; and the bamboo plywood is dismantled to obtain the semicircular pile. In the whole construction process, only materials such as bamboo plywood and steel bars which are easy to purchase and low in price need to be input, so that the cost input is reduced, and the economical efficiency of the whole project is improved. Meanwhile, the bamboo plywood is easy to detach, noise is greatly reduced, the requirement for green construction is met, and the problems that semicircular pile construction is troublesome and engineering quality is difficult to guarantee are solved.

Description

technical field [0001] The invention discloses and belongs to the technical field of building construction, and in particular relates to a construction method for covering and excavating semi-circular piles in a station. Background technique [0002] The enclosure piles of the cover and excavation station include semi-circular piles and round piles, and the upper part of the enclosure piles is designed as a semi-circular pile. [0003] In the current construction process, the enclosing piles are poured into a circle as a whole, and then the upper part is formed into a semi-circular pile by manual breaking. Then, when the half-pile is demolished in the foundation pit, it is difficult to control the flatness of the base surface due to the cumbersome process and the difficulty in accurately controlling the demolition range. At the same time, the construction efficiency is low and the overall construction cost is high. In addition, the position of the half-width reinforcement c...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Applications(China)
IPC IPC(8): E02D5/34E02D5/38E02D29/02
CPCE02D5/34E02D5/38E02D29/02
Inventor 高文华刘石磊姜山刘一锋郝琪琪张海洋曹彦华耿凯旋
Owner CHINA RAILWAY NO 3 GRP CO LTD