Open cut tunnel and bridge combined underpinning integrated construction method

A construction method, technology of open-cut tunnels, applied in excavation, bridges, bridge construction, etc., can solve problems such as heavy traffic flow, difficulty in meeting the goal of normal passage of upper bridges, and inability of tunnels to pass through under or in the middle of pile foundations

Pending Publication Date: 2022-07-08
SHANGHAI CONSTRUCTION GROUP
View PDF9 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

Since the East-West Avenue is the main road in the city, vehicles pass frequently and the traffic flow is huge. The construction party requires that the tunnel crossing construction must ensure the normal traffic capacity of the elevated road. Therefore, the feasibility of the reconstruction plan is ruled out. Arranged so that the tunnel cannot pass under or through the pile foundations
The existing conventional foundation pit cut-and-cut support technology is difficult to meet the goal of rapid construction of the lower tunnel and the normal passage of the upper bridge

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Open cut tunnel and bridge combined underpinning integrated construction method
  • Open cut tunnel and bridge combined underpinning integrated construction method
  • Open cut tunnel and bridge combined underpinning integrated construction method

Examples

Experimental program
Comparison scheme
Effect test

Embodiment 1

[0037] Combine below Figure 1 to Figure 3 , describe in detail the open-cut tunnel combined with bridge underpinning integrated construction method of the present invention.

[0038] Please refer to Figure 1 to Figure 3 , an integrated construction method for open-cut tunnels combined with bridge underpinning, the construction method comprising the following steps:

[0039] Step S1, constructing supporting piles 8, underpinning piles 13, foundation pit enclosure piles 9 in adjacent areas and shared enclosure piles 21 around the old cap 3;

[0040] Step S2, setting the auxiliary pier 6, under the action of the jacking monitoring system 5, the auxiliary pier 6 lifts the holding force, and the auxiliary pier 6 is used to carry out the construction of the hoop 7 to the column 2, so that the column below the hoop 7 of the auxiliary pier 6 is constructed. in a state of zero stress;

[0041] Step S3, excavation is carried out around the underpinning platform 12 to be built to th...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

The invention provides an open cut tunnel and bridge underpinning combined integrated construction method, belongs to the technical field of rail transit deep foundation pit engineering, and aims to meet the requirements of rapid construction of an underpass tunnel and normal passage of an upper bridge at the same time. The method comprises the steps that firstly, supporting piles, underpinning piles and fender posts are constructed; 2, the jacking holding force of the auxiliary pier is set, and the stand column is hooped; thirdly, slope excavation is conducted till the underpinning bearing platform bottom is reached, stand columns are cut off, and old bearing platforms and old pile foundations which conflict with the tunnel structure and the first horizontal supports at the upper end and the lower end are chiseled away; fourthly, water cutting is conducted on stand columns, a top ring beam and first horizontal supports at the upper end and the lower end are constructed, and then an underpinning bearing platform is constructed; fifthly, after the underpinning bearing platform reaches the design strength, the auxiliary piers are dismantled, the bearing piles are pulled out, and pile bodies on the upper portions of the shared fender posts are cut off to the elevation of the top ring beam; sixthly, foundation pit earth excavation is conducted layer by layer, and supports below the first horizontal supports at the upper end and the lower end are poured and erected; and seventhly, after excavation is conducted to the base, a tunnel structure is built back, the horizontal supports are dismantled, and construction is completed.

Description

technical field [0001] The invention relates to the technical field of rail transit deep foundation pit engineering, in particular to an integrated construction method for open-cut tunnels combined with bridge underpinning. Background technique [0002] The east-west expressway underpass project of a project includes ground roads and underpass tunnels. The project is arranged along the east-west avenue of the main road in the existing urban area. After passing through a section of ground, it will continuously pass through the provincial road and the viaduct in the form of tunnels, and the main line tunnel will pass through the high-speed ramp bridge and the main viaduct bridge. Among them, most of the pier caps of a certain bridge are located inside the west line tunnel, which interferes with the plane of the west line tunnel, and there is a plane conflict between the two. The pile foundation of the cap will hinder the excavation of the tunnel foundation pit. The plan origi...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
Patent Type & Authority Applications(China)
IPC IPC(8): E02D27/12E02D27/14E02D17/04E01D22/00
CPCE02D27/12E02D27/14E02D17/04E01D22/00Y02A30/60
Inventor 林巧郑凤先钟铮薛九天
Owner SHANGHAI CONSTRUCTION GROUP
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products