A construction method and long-span technology, applied in bridges, bridge construction, bridge materials, etc., can solve the problems of high construction difficulty, high engineering risk, and low economic benefits of long-span steel box double-arch bridges, and achieve convenient equipment selection and material acquisition , Guarantee the quality of the project and reduce the effect of on-site work

Pending Publication Date: 2022-07-26
河北省高速公路延崇管理中心(河北省高速公路京雄管理中心) +1
View PDF5 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0003] At present, there are certain deficiencies in the construction of long-span steel box double-arch bridges. During the construction of steel box girders, the large sections of steel box girders are not easy to transport and assemble, which makes the construction of long-span steel box double-arch bridges difficult. Higher, and the construction period is long, the economic benefit is low, and the project risk is relatively high, which is not conducive to the needs of construction

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Construction method of large-span steel box continuous arch bridge
  • Construction method of large-span steel box continuous arch bridge
  • Construction method of large-span steel box continuous arch bridge

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0041] The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the embodiments of the present invention. Obviously, the described embodiments are only a part of the embodiments of the present invention, rather than all the embodiments. The embodiments in this application and the features in the embodiments may be combined with each other without conflict. Based on the embodiments of the present invention, all other embodiments obtained by those of ordinary skill in the art without creative efforts shall fall within the protection scope of the present invention.

[0042] It should be noted that if there are directional indications (such as up, down, left, right, front, back, etc.) involved in the embodiments of the present invention, the directional indications are only used to explain the relationship between various components in a specific posture If the specific posture changes, the directional ind...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

The invention discloses a construction method of a large-span steel box continuous arch bridge. The construction method comprises seven steps of dividing large sections of steel box girders, arranging shortcuts and gantry cranes, arranging a steel trestle, erecting a bracket, assembling the steel box girders, mounting other hole span steel girders and dismounting the bracket. According to the steel box girder, large-section splicing, flat car transportation and gantry crane hoisting are completed in a splicing field, the welding work amount of field installation is reduced, the project quality is guaranteed, before installation construction, through the BIM virtual installation technology, the problems occurring in the installation process of the large sections of the steel bridge are found out, an optimal correction scheme is given, and the construction efficiency is improved. Field work is reduced, and construction quality is improved.

Description

technical field [0001] The invention relates to the technical field of building construction, in particular to a construction method of a large-span steel box continuous arch bridge. Background technique [0002] With the rapid development of my country's economy, the requirements for transportation are increasing day by day, and steel structure bridges play an irreplaceable role as an important infrastructure. Especially the long-span steel box double-arch bridge is favored by people for its unique structure and beautiful shape, and is widely used in the construction of highway transportation infrastructure. [0003] At present, there are certain deficiencies in the construction of long-span steel box double-arch bridges. During the construction process of steel box girders, the large sections of the steel box girders are inconvenient to transport and inconvenient to assemble, which leads to the construction difficulty of long-span steel box double-arch bridges. It is rela...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
Patent Type & Authority Applications(China)
IPC IPC(8): E01D21/00E01D12/00E01D101/24E01D101/30
CPCE01D21/00E01D12/00E01D2101/24E01D2101/30
Inventor 闵雪峰刘欣超彭亚涛刘于志刘金竹王岩
Owner 河北省高速公路延崇管理中心(河北省高速公路京雄管理中心)
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products