Concrete structural joint reverse construction method waterproof sealing structure and construction method thereof
A concrete structure, waterproof sealing technology, applied in the direction of basic structure engineering, water conservancy engineering, underwater structures, etc., can solve the problems of difficult repair of waterproof structures, damage repair, etc., and achieve the effect of convenient repair and water leakage
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0051] In the following, relevant embodiments are introduced in conjunction with the waterproof structure solution with post-casting construction joints.
[0052] like figure 1 As shown, this embodiment includes a base layer 1 on the water-facing surface, a waterproof reinforcement layer 2, a structural layer 3, and a structural joint 4 formed by a post-casting tape.
[0053] Structural joints 4 are formed at the junctions of successive pouring, and three reserved passages 5 and grouting conduits 6 connected to the upper and lower structural joints 4 of the post-casting belt are respectively provided, because the upper and lower parts of the structural joints 4 formed by the post-casting belt are the same. However, for the convenience of description, the following only introduces the waterproof structure at the upper structural seam 4 of the post-casting belt.
[0054] like figure 2 As shown, sealing plugs 7 are installed at the ports of the grouting conduit 6, which are re...
Embodiment 2
[0068] like Figure 4 As shown, the difference between the second embodiment and the first embodiment is that, in order to speed up the construction progress, simplify the waterproof structure, and save costs, the waterproof reinforcement layer 2 may not be provided between the structural layer 3 and the water-facing base layer 1 . At this time, the structural joint 4 formed by the post-casting belt is directly connected to the above-mentioned base layer 1 on the upstream surface, and its waterproof structure is composed of the waterproof structure in the structural joint and the independent continuous cavity of the concrete structure formed by the reserved channel 5 and the grouting pipe 6 .
Embodiment 3
[0070] like Figure 1-Figure 4 As shown, the present embodiment provides a construction method of a concrete structure joint reverse method waterproof sealing structure, comprising the following steps:
[0071] S1: Based on the pre-set construction requirements, carry out the construction of the base layer 1 on the upstream surface, and lay a waterproof reinforcement layer 2 on the back surface of the base layer 1 on the upstream surface;
[0072] S2: Set up steel mesh on the back of the waterproof reinforcement layer 2, install the structure layer 3 pouring template on the outer surface of the steel mesh, install the degradable pipe at the steel mesh position of the preset structural joint 4, and install the degradable branch pipe according to the design requirements. , one end of the degradable branch pipe is connected to the degradable pipe, and the other end extends to the outside of the pouring formwork, and then concrete pouring;
[0073] S3: Curing and demoulding the c...