Looking for breakthrough ideas for innovation challenges? Try Patsnap Eureka!

Construction method for preventing slurry from overflowing in underground diaphragm wall pouring construction

A construction method, the technology of ground connection wall, which is applied in the direction of construction, sheet pile wall, foundation structure engineering, etc., can solve the problems of wall mud overflow, increase the total amount of mud, and enter the guide wall, so as to avoid mud overflow and reduce the overall The effect of reducing the amount and reducing the overall cost

Pending Publication Date: 2022-08-05
CCCC SECOND HARBOR ENG
View PDF6 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0005] The technical problem to be solved by the present invention is to provide a mud spill prevention construction method used in the ground wall pouring construction, to solve the problem that the retaining wall mud overflows and enters the guide wall during the construction of the ground wall, and to avoid on-site pollution caused by mud and The problem of cost increase caused by increasing the total amount of mud is used to achieve the goal of zero pollution and low cost in the construction of ground-to-wall construction

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Construction method for preventing slurry from overflowing in underground diaphragm wall pouring construction
  • Construction method for preventing slurry from overflowing in underground diaphragm wall pouring construction
  • Construction method for preventing slurry from overflowing in underground diaphragm wall pouring construction

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0033] like Figure 1-6 Among them, a mud spill-proof construction method used in the construction of ground connecting wall is characterized by comprising the following steps:

[0034] 1) Before excavation of the first-phase groove 1 of the ground-connecting wall, excavate the area between the first-phase groove 1 of the ground-connecting wall and the guide wall 3 at the top of the adjacent unexcavated area 6, and the excavation scope is the design bottom elevation of the guide wall 8 to the design bottom elevation of the crown beam 9, the mud buffer zone 2 will be formed after the excavation is completed;

[0035] 2) Lay a slurry discharge pipe 4 in the mud buffer zone 2, and the slurry discharge pipe 4 is connected to the mud pump 5;

[0036] 3) Carry out the excavation of the first-phase groove 1 of the ground connecting wall;

[0037] 4) Carry out the first sealing operation of groove 1 of the first phase of the ground connection wall;

[0038] 4.1) A pouring frame is ...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

A slurry overflow prevention construction method used in underground diaphragm wall pouring construction comprises the following steps that (1) before an underground diaphragm wall first-stage groove is excavated, the underground diaphragm wall first-stage groove and an adjacent non-excavated area are excavated to form a slurry buffer area; 2) laying a slurry discharge pipeline in the slurry buffer area, wherein the slurry discharge pipeline is connected to a slurry pump; (3) a first-stage groove of the diaphragm wall is excavated; (4) first sealing operation of a first-stage groove of the diaphragm wall is carried out; (4.1) a pouring frame is erected above the first-stage groove of the underground diaphragm wall, and concrete pouring is conducted; 4.2) continuously extracting the slurry overflowing into the slurry buffer area by a slurry pump; (5) after the first sealing operation is completed, concrete is continuously poured; by the adoption of the method, the problem that wall protecting slurry overflows and enters a guide wall in the underground diaphragm wall construction process is solved, the problems that site pollution is caused by the slurry and cost is increased due to the fact that the total using amount of the slurry is increased are solved, and the purposes of zero pollution and low cost of underground diaphragm wall construction are achieved.

Description

technical field [0001] The invention relates to the technical field of bridge construction, in particular to a mud overflow prevention construction method used in the pouring construction of ground connecting walls. Background technique [0002] The underground diaphragm wall is a kind of grooving machine used on the ground in the foundation project. Along the peripheral axis of the deep excavation project, under the condition of mud wall protection, a narrow and long deep groove is excavated. After the groove is cleared, it is suspended in the groove. Place the steel cage, and then use the conduit method to pour the underwater concrete into a unit groove section. This is done section by section, and a continuous reinforced concrete wall is built underground as a water interception, anti-seepage, load-bearing and water-retaining structure. [0003] In the construction process of pouring the concrete into the groove of the ground connecting wall, in order to avoid the inclusi...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
IPC IPC(8): E02D5/18E02D15/00
CPCE02D5/187E02D15/00
Inventor 陈诚付望林杜磊叶鹏李天豪史浩博刘礼赟高才刘超叶光清李航赵立豪徐宗凌付柄鑫简祖泽张中琦
Owner CCCC SECOND HARBOR ENG
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Patsnap Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Patsnap Eureka Blog
Learn More
PatSnap group products