Construction method of guarantying pile length of driven cast-in-place pile constructed in pebble layer or sand layer

A technology of immersed tube grouting piles and construction methods, which is applied in the direction of sheet pile walls, foundation structure engineering, construction, etc., can solve the problems of high natural strength, the depth of immersed tubes cannot meet the design requirements, and the difficulty of immersed tubes, etc., and achieve reduction Effect of Immersed Tube Resistance

Inactive Publication Date: 2008-10-08
刘清洁
View PDF0 Cites 6 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0002] Invention patent application "construction method of sinking cast-in-situ piles in pebble layer and sand layer to ensure pile length" (patent application number: 2007101885943) discloses a method of constructing piles in pebble layer, round gravel layer, breccia layer, sand layer...

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Examples

Experimental program
Comparison scheme
Effect test

Embodiment 1

[0013] The general situation of this embodiment is: a certain project has 12 floors on the ground, one floor underground, and the buried depth of the foundation is 6.0m, and the natural foundation scheme is not established. Construction area 28000m 2 , the design foundation form is piles under the wall, strip foundation, and the pile type is designed as a compact sinking tube expansion rammed reinforced concrete big head pile. The parameters of the design pile are: pile diameter Φ450, pile length 6.5m, and the pile end enters ③ layer of sand More than 1.5m, the expansion head at the bottom of the pile is 0.5m 3 , the concrete strength is C35, the main reinforcement is set to 6Φ14, and the standard value of the ultimate bearing capacity of a single pile is 2600KN. The general situation of the formation is as follows: ①The characteristic value of the bearing capacity of the sand layer under the foundation is 140kpa, the thickness is 1.8-2.5m, and the number of standard inertial...

Embodiment 2

[0016] The general situation of this embodiment is: a certain project has 26 floors on the ground, one floor underground, a frame-shear structure, and the buried depth of the foundation is 7.0m. The natural foundation scheme is not established. The second layer of pebble layer based on the original geological situation, the characteristic value of natural bearing capacity is 200kpa, the thickness of this layer is 1.5-5.5m, and the standard inertia number is 11-27. The distribution of the strata is uneven. The third layer is silty clay, the characteristic value of bearing capacity is 180kpa, and the thickness of this layer is 3.5-5.0m. The fourth layer is a pebble layer, the characteristic value of bearing capacity is 280kpa, and the standard inertia number is 21-32 The thickness of this layer is 8.3-9.5m. The bearing layer at the pile tip of this project is 1m into the pebble layer of layer ④, the designed pile length is 9.5m, the pile diameter is Φ350, and the main pile is fil...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

PropertyMeasurementUnit
Diameteraaaaaaaaaa
Lengthaaaaaaaaaa
Lengthaaaaaaaaaa
Login to view more

Abstract

The invention relates to a construction method which can be constructed at a gravel layer, a round gravel layer, a breccia layer, a sand layer or a strong weathered mudstone and can ensure the constructive pile length to meet the design requirements. The construction method is characterized in that: Firstly, an inner pipe with an opening at the bottom is arranged inside an outer pipe with an opening at the bottom, and then the base of a heavy punch is arranged on a round steel plate at the top of the inner pipe. Secondly, the heavy punch is started to hammer the round steel plate at the top of the inner pipe, so that the inner pipe and the outer pipe can be sunk into the bed soil; when the cast-in-place pile is difficult to be implemented, but the constructive pile length can not meet the design requirements, the inner pipe is drawn out, and the filler crushed inside the inner pipe in cast-in-place pile is cleared, and then the inner pipe is inserted into the outer pipe again, after that, the heavy punch is restarted to hammer the round steel plate at the top of the inner pipe so as to make the inner pipe and the outer pipe sink into the bed soil, such process is repeatedly. Thirdly, the inner pipe is drawn out, and a steel cage is arranged into the outer pipe, and the outer pipe is poured with concrete. Fourthly, the surface of the concrete inside the outer pipe is pressed by the inner pipe in which the filler is cleared, and then the outer pipe is pulled out in uniform speed slowly. Fifthly, when all the outer pipes are pulled out, the pipe is vibrated by a vibrating spear. The filler which is squeezed into the inner pipe is cleared repeatedly, thereby the depth of the cast-in-place pile can meet the designed pile length.

Description

technical field [0001] The invention relates to a construction method of concrete pouring piles, in particular to a construction method which is constructed in a pebble layer, a round gravel layer, a breccia layer or a sand layer and can ensure that the length of the construction pile meets the design requirements. technical background [0002] Invention patent application "construction method of sinking cast-in-situ piles in pebble layer and sand layer to ensure pile length" (patent application number: 2007101885943) discloses a method of constructing piles in pebble layer, round gravel layer, breccia layer, sand layer or strong wind The method of constructing compact immersed pipe grouting piles in geology such as mudstone, but the natural strength of this kind of geology is relatively high, and the immersed pipe is difficult, and the depth of the immersed pipe often fails to meet the design requirements. Contents of the invention [0003] The purpose of the present inve...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
IPC IPC(8): E02D5/38
Inventor 刘清洁
Owner 刘清洁
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products