Construction process for smoke canal swinging assembly of sintering device
A construction technique and flue technology, which is applied in the direction of combustion method, combustion product treatment, furnace type, etc., can solve the problems that the flue cannot be installed in place, the space for crane passage is limited, and the installation period is extended, so as to shorten the installation period. The effect of shortening the transportation and installation period, reducing the cost of hoisting and installation, and reducing the cost of engineering construction
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Examples
Embodiment Construction
[0018] The construction technology of the sintering machine flue lifting group pair of the present invention, its steps are:
[0019] 1. Make the flue hoisting section and the flue support. The length of each flue hoisting section is 1 to 2 times the length (axle span) between adjacent foundation axes of the factory building, 3 times the original flue design section and Above; install and fix the flue support in place according to the design requirements. Usually the wheelbase (axle span) between columns of the sintering main workshop is generally 6 meters or more, and the length of each section of the flue hoisting section is designed to be 1 to 2 times the length of the shaft span, which can reach 10 meters or more. The length of the flue is usually 1 / 2 to 1 / 3 of the length of the shaft span, generally 2 to 3 meters; it can greatly reduce the cost of manufacturing, transportation and installation of small segment flues.
[0020] 2. On the load-bearing beam (frame beam) wher...
PUM
Login to View More Abstract
Description
Claims
Application Information