Inside spraying construction method of pellet roasting vertical furnace

A construction method and internal spraying technology, which is applied in the field of spraying construction in the pellet roasting shaft furnace, can solve the problems of long maintenance period during shutdown period, high maintenance cost, easy loosening and falling off, etc., to achieve isolation from direct erosion and reduce maintenance costs , Improve the effect of roasting quality

Inactive Publication Date: 2010-01-20
CHONGQING IRON & STEEL (GRP) CO LTD
View PDF0 Cites 8 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

The traditional maintenance treatment method is grouting treatment, that is, in the outermost steel plate of the furnace body, between the damaged asbestos layer and the refractory brick layer, pour repair slurry to repair the damaged part; this kind of grouting treatment method, there are The following points are insufficient. First, the maintenance cost is high, and the annual grouting cost alone reaches more than 300,000, which increases the production cost accordingly; The bonding between the furnace bodies is not firm, and it is easy to loosen and fall off; the third is that the use time is short, and grouting needs to be repeated many times, basically once a month; the fourth is the shutdown period (including the maintenance period) required for each grouting are long, affecting the normal production
Grouting the pellet roasting shaft furnace can no longer meet the actual needs of steelmaking production

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0017] The spraying construction method in the pellet roasting shaft furnace of the present invention is characterized in that it comprises the following steps:

[0018] 1. According to the actual situation of the damage of the roasting shaft furnace, formulate the spraying parameters and spraying process, and determine the air pressure (air volume), water pressure, spraying volume and other parameters of the spraying machine used; the commonly used related parameters are as follows: spraying machine spraying volume 2~4.8m 3 / hour, water pressure between 0.5 ~ 0.7MPa, air volume between 5 ~ 10m 3 / minute, can achieve the ideal spraying effect.

[0019] 2. Clean the furnace wall of the roasting shaft furnace to remove the burnt furnace wall and other impurities;

[0020] 3. According to the requirements of the spraying process, several layers of steel wire mesh are installed (usually welded) on the furnace wall to form a steel wire mesh layer that is mutually pulled (connec...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention discloses an inside spraying construction method of a pellet roasting vertical furnace, comprising the following steps: 1, determining that the ejection quantity of a used spraying machine is 2-4.8m<3> / hours, water pressure is between 0.5MPa and 0.7MPa, and the wind quantity is 5-10m<3> / minutes; 2, cleaning a furnace wall of the roasting vertical furnace; 3, arranging a plurality of layers of steel wire mesh layers which are mutually pulled and have firm structures on the furnace wall; 4, firstly adding water for wetting before adding spraying paint into the spraying machine and controlling the water content between 2% and 4%; 5, firstly curing in natural state for 6-15 hours after spraying to spontaneously cure a spraying layer; then, raising temperature and roasting, keeping the initial temperature rise speed at 15-25 DEG C / hours, and then, keeping the temperature between 130 DEG C and 170 DEG C for 3-8 hours; and then, raising temperature at the rise speed of 30-50 DEG C / hours until the finish of roasting. The construction method of the invention effectively solves the phenomena of reddening, deformation, wind escape and air leakage of the roasting vertical furnace, enhances the roasting quality of pellets and prolongs the service life of the roasting vertical furnace; the use time is long, and the maintenance expense and the production cost are lowered.

Description

technical field [0001] The invention relates to a maintenance and construction method of a roasting pellet shaft furnace in a steelmaking system, especially a pellet roasting method used in maintenance after the roasting pellet shaft furnace has air leakage, deformation, redness and other phenomena. The construction method of spraying in the shaft furnace. Background technique [0002] The pellet roasting shaft furnace used by the applicant, after many years of use, the furnace body is seriously aging, the temperature in many places of the furnace body is high, and even redness, deformation, air leakage and air leakage have occurred, which greatly affects the normal production. Production, quality and safety have brought negative effects, restricting the improvement of pellet roasting quality. The main reason is that the inside of the shaft furnace is in a state of dynamic equilibrium. On the one hand, the material column moves from top to bottom, forming a scour to the inn...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Applications(China)
IPC IPC(8): F27D1/16
Inventor 王才文胡钢
Owner CHONGQING IRON & STEEL (GRP) CO LTD
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Patsnap Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Patsnap Eureka Blog
Learn More
PatSnap group products