Construction process of floral tube dry filling piles

A construction process and cast-in-place pile technology, which is applied in sheet pile walls, infrastructure engineering, construction, etc., can solve the problems of long mixing time interval, poor upper compactness, and large thickness of mud around the pile.

Inactive Publication Date: 2012-10-17
HENAN UNIVERSITY
View PDF0 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0014] 3) The process of making and installing the reinforcement cage is complicated:
[0027] (4) Multiple high-pressure injections of cement slurry are required
[0029] 4. Problems and deficiencies in the above process
On the other hand, the unreasonable adjustment of mud consistency and mud material selection for the retaining wall is the direct factor leading to the failure of reducing the water loss of plastic soil (controlling the seepage reduction of the hole wall) and the failure to quickly form a stable hole wall mud skin around the hole wall
Thirdly, when the hole is formed, the mud delivery rate of the mud pump is not increased, the hole is not formed quickly, and the time for forming the hole is not shortened, which is the indirect cause of swelling, quicksand and soil collapse.
Fourth, a certain number of alloy blades are not welded on the outside of the straightener, and the sweeping effect does not work when drilling or pulling out, which is an improper control factor
[0049] The concrete in the pile body is discontinuous after solidification, and the broken pile phenomenon that the pile body is partially filled with mud, uncured concrete and soil is mostly caused by: the distance between the bottom end of the conduit and the bottom of the hole is greater than 1.0m, that is, the exit of the conduit is too close to the bottom of the hole; the concrete pouring process Diluted by the water in the mud, the amount of water in the water-cement ratio in the concrete increases, delaying the age of concrete solidification; affected by groundwater activities or poor sealing of the conduit, groundwater immerses in the concrete to change the water-cement ratio, resulting in slow piles. Condensation; the lifting and pulling speed of the conduit is greater than the concrete pouring speed, and the bottom of the conduit is exposed to the concrete surface in the hole, that is, the conduit is lifted too fast; or temporary power failure, long intervals of concrete mixing cause slag inclusion, and mud sediment deposits in the pile hole Layers; when pouring concrete, instead of pouring it from the conduit, the concrete is poured directly from the orifice, resulting in concrete segregation, resulting in looseness and voids in individual piles.
[0050] ③ Poor compactness of pile concrete
[0052] ④ thick mud skin around the pile
[0055] ①The process of making steel cages is complicated:
However, cast-in-situ piles belong to the field operation process. Therefore, the mix ratio of concrete will change due to factors such as mixing location, humidity in the air, moisture content and particle size of sand and gravel, and different batches of cement. The mix ratio of the concrete in it is substantially different from the mix ratio provided by the laboratory
[0071] 2) Problems and deficiencies in the construction technology of special cast-in-place piles
[0073] ① Unable to determine the fullness and compactness of the cement slurry in the sand
[0079] The proportion of cement particles is larger than that of cement slurry. Under the action of gravity and during the process of cement gel production, cement particles are mostly deposited in the middle and lower parts of the pile body. Therefore, the strength of the pile body in the middle and lower parts of the pile body is greater than that of the pile body. The strength of the middle and upper parts, the compactness of the upper part is poor, and the coagulation strength is low
The strength of the main stress-bearing part of the pile body (pile top) is low
[0080] 3) Problems and deficiencies in construction workers of advanced micro piles (small piles without sand)
[0082] ① Unable to determine the fullness and compactness of the cement slurry in the gravel
[0089] ④ Poor bonding between step-by-step concrete and steel pipes
This kind of pile is only suitable for projects with relatively low loads in engineering applications.
[0091] ⑤ The strength of concrete is difficult to meet the design requirements
[0092] Due to the lack of intermediate particles and the cement solidification body cannot fill all the coarse particle spaces, the strength of the step-by-step concrete is tested under the same cement content. The results of the pressure test show that the unconfined compressive strength does not meet the design requirements
[0093] ⑥ The construction process is cumbersome and labor-intensive
[0097] Through the above brief introduction, the construction process of cast-in-situ piles is complicated, lacks clear indicators, has no obvious effect, is not high in safety, is difficult to master, low in economy, high in mechanical cooperation, high in labor intensity, many testing items, complex in management, and difficult to supervise. Many contents, changeable process control factors, strong comprehensiveness, lack of understanding and utilization of natural geotechnical engineering conditions, weak improvement, non-uniform quality caused by non-standardized process flow, etc. have become obstacles to the development of cast-in-place pile technology

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Construction process of floral tube dry filling piles
  • Construction process of floral tube dry filling piles
  • Construction process of floral tube dry filling piles

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0239] The flower tube dry cast-in-situ pile is composed of dry concrete, flower tube and other items. The specific process steps of implementation can be divided into four process parts. Each part is introduced in detail as follows:

[0240] 1. Hole forming process:

[0241] 1) Hole-forming piles above the groundwater level

[0242] Adopt dry hole-forming process: mechanical, manual and other traditional hole-forming processes. The form is determined according to the specific geological conditions and does not need to be improved.

[0243] 2) Hole-forming piles below the groundwater level

[0244] This process is suitable for engineering sites with geological conditions such as sand layer, silt layer, cohesive soil layer interbed or the combined stratum among them.

[0245] Drilling → drill in place → low stroke, high-speed rotation, clean water drilling → reach the drilling depth → unified stroke, high-speed rotation, clean water lift stop hole → unified stroke, high-spee...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

The invention relates to a construction process of floral tube dry filling piles with obvious engineering effect, low economic cost, high technical content and high resource utilization by improving the inherent characteristics of cement, soil strata, materials and the like. The process comprises the following steps of: (1) pore-forming process: 1, using dry pore-forming process for pore-forming piles above underground water level; 2, positioning a pore opening machine and a drill for pore-forming piles below underground water level; drilling in at low stroke and high rotary speed with clean water; reaching a drilling-in depth; lifting to a pore opening at unified stroke and high rotary speed with clean water; drilling into a pore bottom at unified stroke and high rotary speed with clean water; rotating at high speed and filling with cement mortar; and lifting to the pore opening at high rotary speed and low stroke after cement mortar returns to the pore opening; moving the drill; (2)the process of installation and pile molding by filling: adopting the following steps for installing pile pores and filling dry cement above or below water level: installing floral tubes; correcting the pore position of the floral tubes; filling the dry cement; and filling the dry cement to an elevation required by the design.

Description

technical field [0001] The invention belongs to the construction technology of building foundation, in particular to the construction technology of cast-in-situ piles. Background technique [0002] From the classification of cast-in-place piles, flower tube dry-process cast-in-place piles belong to hole-forming cast-in-place piles. Its technology and process are similar to ordinary cast-in-place piles, special cast-in-place piles, advanced micro piles - small piles without sand, etc., but there are great differences. In order to more clearly introduce the characteristics of the flower tube dry cast-in-place pile, through engineering practice, the concrete production process and the production of the steel cage (or steel pipe) in the previous construction technology of the cast-in-place pile are summarized, summarized and classified. Explain the difference with the existing cast-in-place pile construction technology. [0003] Concrete classification: The concrete in the fil...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
Patent Type & Authority Patents(China)
IPC IPC(8): E02D5/34
Inventor 吴保全
Owner HENAN UNIVERSITY
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products