Method for constructing isolation pile for shield tunnel to go through deformation control of buildings and structures at short distance
A shield tunneling and deformation control technology, applied in building construction, construction, building maintenance, etc., can solve problems such as the inability to meet and protect settlement requirements for historical and ancient buildings, so as to reduce soil loss, reduce noise, and avoid impact. Effect
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0022] Such as figure 1 As shown, it is a schematic flow chart showing the construction method of the isolation pile for the deformation control of the shield tunnel passing through the building at a short distance provided by the present invention. The isolation pile construction method for the deformation control of the shield tunnel passing through the building at a short distance is used for shield construction When passing through in a short distance, the settlement is controlled to protect historical buildings. The implementation steps of the isolation pile construction method of the shield tunnel passing through the deformation control of the building in a short distance include: pouring a reinforced concrete force transmission platform, continuing the steps of sinking piles to form holes, and Install reinforcement cages and pour concrete, and perform auxiliary grouting measures.
[0023] In the step of pouring the reinforced concrete force transmission platform, accord...