Construction method of BDF thin-wall hollow pipe in cast-in-place hollow floor
A technology of hollow floor and construction method, applied in the direction of floor, building material processing, structural elements, etc., can solve the problems of core tube slippage, affecting project quality, honeycomb, pockmark, holes, etc., to strengthen positioning, improve Reasonable effect of construction quality and construction process
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Examples
Embodiment Construction
[0010] 1. Construction process
[0011] Pre-set core tube positioning bracket, erecting frame, supporting formwork, pre-embedded pipeline, binding plate bottom steel bar, pre-embedded electric tube, welding positioning bracket, inspection line inspection bar, installing core tube, binding plate surface steel bar, welding auxiliary steel bar Mesh sheet, construction access road, acceptance of concealed works, installation of concrete conveying pipe, pouring and pounding concrete, fixing core pipe, concrete maintenance, formwork removal.
[0012] 2. Construction essentials:
[0013] (1) Bent frame: The span and thickness of the plate are relatively large, and the erection of the bent frame based on experience will cause safety hazards or waste of materials. Therefore, the distance between the vertical poles must be determined by calculation, and the distance between the steel pipes must be determined through calculation.
[0014] (2) Spring line: According to the design require...