Method for building vertical breakwater
A technology of embankment head and soft foundation, which is applied in the field of vertical dikes, can solve the problems of large engineering volume, large excavation surface, and slow progress, and achieve the effects of saving dredging costs, speeding up construction progress, and saving stone materials
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0060] In order to make the content and advantages of the present invention clearer, the present invention will be further described in detail below in conjunction with the accompanying drawings and specific embodiments.
[0061] The concrete steps of the vertical dike that uses the present invention to build are as follows:
[0062] Step 1: Select the bearing layer and design the section structure of the vertical embankment. When selecting the bearing layer and designing the section structure of the vertical embankment, the characteristics of the foundation treated by fine blasting and silting should be fully considered to ensure the structural stability of the vertical embankment.
[0063] Step 2: Stone filling. Natural mixed graded stones can be used for throwing and filling stones. The stones are required to be fresh and complete, and the mud content should not exceed 5%. The throwing and filling methods can be water throwing, land throwing, and water and land mixed thro...