Underground diaphragm wall construction method adopting fore shaft pipe joints
A technique for underground diaphragm walls and construction methods, which can be applied to artificial islands, water conservancy projects, underwater structures, etc., and can solve problems such as low construction quality of underground diaphragm walls, poor wall integrity, and hidden construction hazards, etc. Achieve the effect of improving construction quality and reliability, reducing hidden dangers such as leakage, and reliable construction
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Examples
Embodiment 1
[0010] A method for constructing an underground diaphragm wall using lock pipe joints. Before, during, and after the concrete pouring of the underground diaphragm wall, the following steps are carried out sequentially:
[0011] Step 1: before pouring the concrete of the underground diaphragm wall, hoist the locking pipe fixing device above the locking pipe, and use the locking pipe fixing device to hug the locking pipe.
[0012] Step 2: When pouring the concrete of the underground diaphragm wall, pour concrete into the wall section of the diaphragm wall in the slot, insert the lock pipe, and start the lock after 2 hours to 4 hours after the concrete of the diaphragm wall begins to be poured The pipe fixing device makes the locking pipe reciprocatingly twist around its central axis. When reciprocatingly torsion, it first rotates π radians at ω angular speed, and then turns π radians at ω angular speed to complete a reciprocating twist. ω is not less than rad / sec, the frequency...
Embodiment 2
[0016] A method for constructing an underground diaphragm wall using lock pipe joints. Before, during, and after the concrete pouring of the underground diaphragm wall, the following steps are carried out sequentially:
[0017] Step 1: before pouring the concrete of the underground diaphragm wall, hoist the locking pipe fixing device above the locking pipe, and use the locking pipe fixing device to hug the locking pipe.
[0018] Step 2: When pouring the concrete of the underground diaphragm wall, pour concrete into the wall section of the diaphragm wall in the slot, insert the lock pipe, and start the lock after 2 hours to 4 hours after the concrete of the diaphragm wall begins to be poured Tube fixing device, so that the locking tube rotates around its own central axis. When rotating, it continuously rotates clockwise or counterclockwise at an angular speed of ω. Every rotation of 2π radians is a rotation, and ω is not less than rad / sec, the frequency of rotation is not less...
PUM
Login to View More Abstract
Description
Claims
Application Information
Login to View More