A treatment method for the inclined shaft entrance of a subway tunnel with a single-track mining method

A processing method and technology of mining method, applied in tunnels, tunnel linings, shaft linings, etc., can solve the problems of less auxiliary tunnels, complex construction at the intersection of inclined shafts and main tunnels, and short interval tunnels, so as to simplify the construction process. , the effect of reducing costs and shortening the construction period

Active Publication Date: 2017-04-26
CHINA RAILWAY SIYUAN GRP SOUTHWEST SURVEY & DESIGN CO LTD +1
View PDF5 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0002] At present, tunnels in subway intervals are generally constructed using the shield method. There are fewer tunnels in subway intervals constructed using the mining method compared with the shield tunneling method, and because the interval tunnels are generally shorter, when the mining method is used for construction, fewer auxiliary tunnels are set up. Other similar projects When setting the inclined shaft, the construction at the intersection of the inclined shaft and the main tunnel is extremely complicated

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • A treatment method for the inclined shaft entrance of a subway tunnel with a single-track mining method
  • A treatment method for the inclined shaft entrance of a subway tunnel with a single-track mining method
  • A treatment method for the inclined shaft entrance of a subway tunnel with a single-track mining method

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0020] The present invention will be described in further detail below in conjunction with specific embodiments and accompanying drawings. Examples of the described embodiments are shown in the drawings, wherein like or similar reference numerals designate like or similar elements or elements having the same or similar functions throughout. The embodiments described below with reference to the accompanying drawings are exemplary, and are only used to explain the technical solution of the present invention, and should not be construed as limiting the present invention.

[0021] In the description of the present invention, the terms "inner", "outer", "longitudinal", "transverse", "upper", "lower", "top", "bottom" or "front", "rear", "left ", "right" and other indicated orientations or positional relationships are based on the orientations or positional relationships shown in the drawings, and are only for the convenience of describing the present invention and do not require tha...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention provides a treatment method of single-line mining method subway tunnel inclined shaft top-hole displacement. The treatment method comprises the steps that the position close to a top hole and needed to be passed through is constructed according to a general inclined shaft cross section, wherein an inclined shaft comprises an inclined shaft wall, the inclined shaft wall is formed by adopting a preliminary bracing and secondary lining combined process; a new cross section is established in the inclined shaft and rightly faces a top-hole section, the inclined shaft is closed by adopting an end wall when construction is performed on the edge of the top hole, preliminary bracing is conducted on the top hole through stepped method construction, and top-hole secondary lining is conducted on a lining trolley during gradual advancing; the new cross section can be constructed before or after top-hole construction and while top-hole construction. Therefore, the technical problems of construction process simplification and construction period shortening are solved, cost reduction is achieved, and good effect of project progress acceleration is achieved.

Description

technical field [0001] The invention relates to the technical field of tunnel construction, in particular to provide a treatment method for the inclined shaft of a subway tunnel with a single-track mining method. Background technique [0002] At present, tunnels in subway intervals are generally constructed using the shield method. There are fewer tunnels in subway intervals constructed using the mining method compared with the shield tunneling method, and because the interval tunnels are generally shorter, when the mining method is used for construction, fewer auxiliary tunnels are set up. Other similar projects When setting the inclined shaft, the construction at the intersection of the inclined shaft and the main tunnel is extremely complicated. Through earnest research and experiments, the inventor has designed a design that can simplify the construction process, speed up the construction period, and can conveniently solve the technical problems of construction at the in...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Patents(China)
IPC IPC(8): E21D9/00E21D11/00
CPCE21D9/00E21D11/003
Inventor 裴利华周华龙
Owner CHINA RAILWAY SIYUAN GRP SOUTHWEST SURVEY & DESIGN CO LTD