A method for judging the timing of converter double slag lifting gun

A converter and timing technology, applied in the direction of manufacturing converters, etc., can solve the problems of large deviation, low success rate, and judgment of the timing of double slag lifting in the converter, and achieve the effect of accurate judgment and significant economic benefits.

Active Publication Date: 2018-06-19
TANGSHAN STAINLESS STEEL +1
View PDF2 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

However, due to the complexity of the melt pool reaction in the early stage of blowing and the change of raw material conditions such as molten iron, the success rate is not high; some steel mills use manual observation of the flame change at the furnace mouth to determine the timing of lifting the gun, and there is a large deviation in judgment based on human experience
So far, there is no particularly effective method for judging the timing of double slag lifting of the converter. Accurately judging the timing of double slag lifting of the converter has become a difficult problem for various iron and steel enterprises, which needs to be solved by professional technicians and workers

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Examples

Experimental program
Comparison scheme
Effect test

Embodiment 1

[0032] 100 tons of converter double slag smelting, furnace input conditions: molten iron C 4.23%, Si 0.76%, P 0.133%, Ti 0.018%, molten iron temperature 1320 ℃. The weight of molten iron is 105.3 tons, and the weight of scrap steel is 15.2 tons.

[0033] Double slag target alkalinity target 1.4, temperature target 1345 ℃ blowing target; through calculation, lime addition is 1.2 tons, limestone addition is 1.1 tons, ore addition is 2.9 tons; oxygen supply intensity is 3.0m3 / (min·t steel ), gun position 2.9 m.

[0034] When the oxygen blowing rate of the converter reaches 14.2%, the flue gas analysis system shows that the CO concentration starts to rise, and when the oxygen blowing rate reaches 23.3%, the CO concentration reaches 27%, and double slag is produced by raising the gun. The measured melting pool temperature was 1355°C, the slag was well melted, and the furnace and slag pouring went smoothly.

Embodiment 2

[0036] 100 tons of converter double slag smelting, furnace input conditions: molten iron C 4.31%, Si 0.84%, P 0.127%, Ti 0.138%, molten iron temperature 1337 ℃. The molten iron weighs 102.3 tons, and the steel scrap weighs 8.3 tons.

[0037] Double slag target alkalinity target 1.4, temperature target 1345 ℃ blowing target; through calculation, lime addition is 1.4 tons, limestone addition is 1.2 tons, ore addition is 3.4 tons; oxygen supply intensity is 2.9m3 / (min·t steel ), the gun position is 2.7 m.

[0038] When the oxygen blowing rate of the converter reaches 14.6%, the flue gas analysis system shows that the CO concentration starts to rise, and when the oxygen blowing rate reaches 20.8%, the CO concentration reaches 23%, and double slag is produced by raising the gun. The measured melting pool temperature was 1340°C, the slag was well melted, and the furnace and slag pouring went smoothly.

Embodiment 3

[0040] 100 tons of converter double slag smelting, furnace input conditions: molten iron C 4.26%, Si 0.89%, P 0.127%, Ti 0.155%, molten iron temperature 1401 ℃. The molten iron weighs 102.3 tons, and the steel scrap weighs 11.6 tons.

[0041] Double slag target alkalinity target 1.8, temperature target 1345 ℃ blowing target; through calculation, the amount of lime added is 2.6 tons, the amount of limestone added is 1.4 tons, and the amount of ore added is 3.2 tons; the oxygen supply intensity is 2.9m3 / (min·t steel ), the gun position is 2.7 m.

[0042] When the oxygen blowing rate of the converter reaches 17.6%, the flue gas analysis system shows that the CO concentration starts to rise, and when the oxygen blowing rate reaches 27.9%, the CO concentration reaches 25.36%, and double slag is produced by raising the gun. The measured molten pool temperature was 1346°C, the slag was well melted, and the furnace and slag pouring went smoothly.

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention discloses a method for judging the timing of double slag lifting of converter, which belongs to the technical field of converter steelmaking operation method, and is used for accurately judging the timing of double slag lifting of converter. The technical solution is: use the carbon monoxide curve in the converter flue gas analysis equipment to determine the temperature of the molten pool, and use it as the basis for judging the timing of double slag lifting. When the flue gas analysis equipment shows that the CO concentration reaches the range of 22-28%, lift the gun Double slag operation. The invention has the characteristics of being able to accurately judge the temperature of the molten pool so as to accurately judge the timing of double slag lifting, and avoids the violent reaction of molten pool carbon due to the low temperature of the molten pool, difficult melting of lime, inability to separate slag and iron, and excessively high temperature of the molten pool after double slag lifting. Cause serious foaming of slag, difficulty in turning down the furnace and other problems. The invention is an innovation in the converter steelmaking method, is particularly effective for judging the timing of double slag lifting of the converter, solves the unresolved problem that has plagued various iron and steel enterprises for a long time, and has significant economic benefits.

Description

technical field [0001] The invention relates to a method for judging the timing of double slag lifting of a converter, and belongs to the technical field of converter steelmaking operation methods. Background technique [0002] Converter double slag is widely used as a process to treat silicon-rich molten iron and reduce steelmaking costs. When the molten iron silicon exceeds 0.7%, the probability of explosive splashing in the converter increases significantly, and various consumption indicators such as steel material consumption deteriorate significantly. The amount of slag can be reduced through double slag, reducing the risk of splashing. For conventional molten iron with low silicon content, some factories adopt the production method of leaving slag and double slag to reduce production costs. [0003] Converter double slag operation is to control the alkalinity in the early stage of blowing to between 1.3-1.8, adopt a suitable oxygen supply system, and when the temperat...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Patents(China)
IPC IPC(8): C21C5/28
Inventor 周泉林李阳邢金栋李鹏刘海波王肖周航赵铁成
Owner TANGSHAN STAINLESS STEEL