Scene visualization intelligent construction site management system based three-dimensional model

A management system and three-dimensional model technology, applied in the field of intelligent chemical site management system, can solve the problems of insufficient intelligence, no three-dimensional display system, no multiple data interaction and application, etc., to achieve the effect of improving the level of intelligence

Active Publication Date: 2016-08-17
SHANDONG ELECTRIC POWER ENG CONSULTING INST CORP
View PDF6 Cites 32 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

The content disclosed in the above-mentioned patents does not have a real scene visualization display based on a 3D model, does not analyze and apply the acquired data in depth, and is not intelligent enough
[0005] In short, the existing technology cannot meet the current needs, and cannot realize the intuitive engineering monitoring based on the real scene on the 3D model, which is mainly manifested in the following aspects:
[0006] 1. The 3D display system is not set up, the corresponding 3D model is not constructed according to the construction site project, and the data acquisition devices corresponding to the man-vehicle management system, construction site video monitoring system, environmental data collection and application system, and information real-time broadcast system are not installed in 3D The real-time deployment and display in the model, the real-time data of the construction site in the form of a 3D view through the smart construction site 3D display system, the integration of various applications of project management, and the realization of multiple project management based on the 3D model of the project The interaction and application of data has not realized the intelligence and intelligence of project management
[0007] 2. The personnel and vehicle information acquired by the access control system has not realized the statistics, analysis, in-depth mining and application of data, and has not provided data interfaces to other functional modules
[0008] 3. The site video surveillance is not integrated into the 3D model of the project, and the position of the video camera is not standardized
[0009] 4. There is no on-site environmental data collection device, and the location of the collection device is not displayed in a three-dimensional view. The relevant data obtained is not set as normal, concerned, and warning data intervals. When the collected data exceeds the standard, there is no alarm or alarm. The means are relatively simple
[0010] 5. The real-time broadcast of on-site information was not realized, the daily automatic scheduled broadcast and the real-time broadcast in case of emergency were not realized, the emergency broadcast triggered by the phone was not realized on-site emergency command, and the broadcast content was not automatically recorded
[0011] 6. The association of project data such as technical documents and management documents with the physical model has not been realized, and it is impossible to view the technical and management documents related to the model in real time
[0012] 7. There is no safety and quality training and examination system dedicated to the project site, and the safety and quality training and examination system does not perform data interaction, association and interaction with systems such as personnel and vehicle management

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Scene visualization intelligent construction site management system based three-dimensional model
  • Scene visualization intelligent construction site management system based three-dimensional model
  • Scene visualization intelligent construction site management system based three-dimensional model

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0039] The present invention is described in detail below in conjunction with accompanying drawing:

[0040] Smart construction site 3D display system: the 3D solid model of the construction project, the people and vehicle management system, the construction site video monitoring system, the safety and quality training and examination system, the environmental data collection and application system, the real-time information broadcast system and the technical document management system, and the management document management The system and other management systems are integrated in the 3D model, through which the intelligent and intelligent management of the construction site can be realized, and the real-time management information and data of the construction site can be displayed in a 3D view.

[0041] Personnel and vehicle management system: Obtain the entry and exit information of personnel and vehicles according to the card swiping information of the access control system...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

The invention discloses a scene visualization intelligent construction site management system based a three-dimensional model, and the system obtains the data of a person and a vehicle according to the card swiping information of an access control system, and obtains the scanning data of a corresponding fixed person and set mechanical equipment through scanning a bar code. A plurality of cameras disposed on a construction site are used for obtaining the real-time video monitoring data of the construction side. An environment monitoring device disposed on the construction site is used for obtaining the corresponding environment data. An information real-time broadcasting system enables the obtained public broadcast data to be transmitted to an information broadcast database. Based on the technology of intelligent construction site management, the visualized scene of the system is displayed and integrated on the basis of the three-dimensional model, and the display, analysis, processing and analysis of the obtained data of the system are carried out. Meanwhile, the system is integrated with the existing project management system and database, thereby achieving the decision support for project management, the bias early warning for a project, and the feedback of project experience and information.

Description

technical field [0001] The invention relates to the field of intelligent industrial sites, in particular to an intelligent industrial site management system based on three-dimensional model-based real-scene visualization. Background technique [0002] Traditional construction management information systems mostly develop project management processes and forms for online circulation according to the needs of project management, and cannot automatically and real-time collect or directly and automatically extract various data generated on the construction site from the system and process the data , did not adopt 3D model and real scene visualization technology, nor integrated into a unified information platform, and could not provide effective decision support for engineering personnel. [0003] Among the existing patents, the application number: 201220675601.9, the application name is: intelligent construction site management system, which specifically discloses: including dig...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
Patent Type & Authority Applications(China)
IPC IPC(8): G05B19/418G06Q50/08
CPCG05B19/41865G05B2219/31457G06Q50/08
Inventor 王琳王作峰张启锡宫俊亭张鲁鹰董长竹潘清波孙晓峰张宝樊俊怀陈文刚
Owner SHANDONG ELECTRIC POWER ENG CONSULTING INST CORP
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products