A method for laying out a leading rope by a helicopter

A technology for guiding ropes and helicopters, which is applied in thin material handling, overhead line/cable equipment, and conveying filamentous materials, etc. It can solve the problems of long time consumption and multiple layers of winding and pulling, so as to reduce work, improve safety and The effect of construction efficiency
CN106451208AActive Publication Date: 2017-02-22国网电力空间技术有限公司 +1

Patent Information

Authority / Receiving Office
CN · China
Current Assignee / Owner
国网电力空间技术有限公司
Publication Date
2017-02-22

Smart Images

  • Figure 1
    Figure 1
  • Figure 2
    Figure 2
  • Figure 3
    Figure 3
Patent Text Reader

Abstract

The invention discloses a method for laying out a leading rope by a helicopter. The method comprises the following steps of setting a special-purpose high speed tension machine in a tension field; placing a leading rope bobbin on a bobbin support; the rope head of the leading rope is lead out through the special-purpose high speed tension machine and line pressing pulleys arranged on the ground. A guide rod type pulley is suspended on a line laying construction position of each base tower; the helicopter drags the rope head of the leading tope and flies over a preset leading rope laying channel. The helicopter flies over the tower so that the leading rope falls into the guide rod type pulley, and the helicopter flies to the next base iron tower. If the bobbin of the leading rope is about to run out, the helicopter hovers; and then the bobbin is changed into a new leading rope bobbin in the tension field, and the helicopter continues to perform flight working until the leading rope goes through the guide rod type pulleys of all the iron towers of a line laying segment. The helicopter flies to an anchor line field at the end of the line laying segment, slowly descends and anchors the leading rope to the ground. According to the invention, a lot of cooperation work by high altitude construction personnel can be reduced so as to greatly raise the security and the construction efficiency.
Need to check novelty before this filing date? Find Prior Art

Description

technical field

[0001] The invention relates to the deployment of high-voltage electric wires, in particular to a method for deploying guide ropes by a helicopter. Background technique

[0002] my country has a vast territory, and the distribution of energy reserves and power loads is uneven. In order to enhance the ability to optimize the allocation of power resources in a wider range and meet the growing demand for electricity in different regions, the construction of large-scale UHV power grids is developing rapidly. UHV line engineering is characterized by high transmission voltage level, large tower tonnage, high height, long span between two adjacent towers, and many crossing conductors. After the UHV iron tower is assembled and accepted, it is necessary to carry out tension setting-out construction to complete the erection of the transmission line.

[0003] The method of laying out the guide (ground) wire by using construction equipment such as tractors and tensione...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine