A compensation method and high filling technology, applied in filling, foundation structure engineering, foundation structure test, etc., can solve the problem of difficulty in establishing the relationship between settlement deformation and compaction degree, failure to meet construction accuracy requirements, uneven settlement, etc. question
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0053] Such as figure 1 As shown, a high fill compaction detection and settlement compensation method based on InSAR technology is characterized in that:
[0054] Step 1. Obtain the SAR image of the constructed high fill: During the process of the constructed high fill from filling to forming, use the airborne interferometric synthetic aperture radar InSAR to measure the constructed high fill, and obtain the image of the constructed high fill within each measurement time Two high-fill single-view SAR images of the construction, and the two single-view SAR images of the high-fill construction obtained during each measurement time are stored in a memory connected to the data processing device; wherein, two The single-view SAR images of the high-filling buildings under construction are all orthophoto images, and the two single-view SAR images of the high-filling buildings under construction are the main SAR images of the high-filling buildings under construction and the SAR auxil...