Foundation pit inner penetrating bottom plate precipitation well plugging construction method
A construction method and technology for dewatering wells, which are applied in the fields of infrastructure engineering, earth-moving drilling, sealing/packing, etc., can solve problems such as leakage of bottom tube wells, blocking of dewatering wells, affecting the normal use function of buildings, etc. The well method is economical, easy to construct, and has good effect.
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Examples
Embodiment Construction
[0045] A construction method for plugging a dewatering well through a bottom plate in a foundation pit, comprising the following steps:
[0046] (1) Manufacture and installation of steel casing
[0047] In order to ensure normal pumping during the construction process, when the basement floor concrete is poured, a waterproof casing must be installed in the downcomer well. The construction of the steel casing includes two aspects: the processing and installation of the steel casing;
[0048] A) Processing of steel casing:
[0049] (1) The steel casing is made of hot-rolled seamless steel pipe with a diameter of 280mm and a wall thickness of 5mm. The height of the steel casing is: the top elevation is 50mm higher than the top surface of the bottom plate, and the overlapping length of the lower end and the dewatering well is 150mm;
[0050] (2) According to the outer diameter of the steel casing, select a steel plate not less than 5mm thick to process the outer waterstop ring, a...