A Construction Method of Sprinkling Water Impact Rolling on Shallow Drought Coral Sand Foundation
A technology of impact rolling and coral sand, applied in infrastructure engineering, construction, soil protection and other directions, can solve the problems of irregular particle shape, filling coral sand foundation can not achieve the best compaction effect, gradation width and other problems
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0034] Example 1: Discussion on the variation of the maximum compacted dry density of dredged coral sand with water content.
[0035] Collect the coral sand (coral gravel soil, coral gravel sand, and coral medium sand) of a reclaimed island reef, add a certain amount of water to it, mix well, and perform drying and water content control according to the geotechnical test procedures. According to the "Standards for Soil Test Methods" (GB / T50123-1999), the maximum compacted dry density is detected, and the trend of the maximum compacted dry density with water content is studied. The test results are as follows: Figure 1-3 shown.
[0036] from figure 1 It can be seen that the maximum compacted dry density of coral gravel soil when dry is 1.85g / cm 3, with the increase of water content, the maximum compacted dry density first decreased and then increased. When the water content was 14%, the maximum compacted dry density reached the minimum value; from figure 2 It can be seen t...
Embodiment 2
[0037] Embodiment 2: A kind of construction method of spraying water and impacting rolling on shallow layer dredging and filling coral sand foundation, such as Figure 4 shown, including the following steps:
[0038] Step 1. The dredged coral sand foundation that has been transferred and refilled on site is relatively loose. Sprinkle water on the surface of the soil, and then fully mix the soil on the surface with the loose soil;
[0039] Step 2. Clean and level the ground after mixing, push it back and forth twice with a bulldozer, and at the same time, sprinkler with sprinkler to ensure that the water content meets the design requirements (water content ≥ 20%);
[0040] Step 3: Use a 25kJ triangular impact roller to impact and roll 20 times at a speed of 10-12km / h until the foundation is compacted. During the impact rolling process, sprinklers cooperate with watering to ensure that the water content meets the design requirements (water content ≥ 20%), the speed of the sprin...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com