A construction method for leaving a structure with construction joints
A construction method and a technology of construction joints, which are applied to building components, building structures, buildings, etc., can solve problems such as difficulty in meeting concrete construction quality requirements and hidden dangers of water seepage, and achieve the effects of avoiding construction hidden dangers, reducing difficulty, and being easy to clean
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0039] Such as Figure 1-4 As shown, this embodiment discloses a construction joint setting structure, the construction joint setting structure is set at the construction joint of the concrete structure, and the construction joint of the concrete structure can be a concrete floor, a floor horizontal construction joint and a shear wall Vertical construction joints; specifically, the construction joint leaving structure includes a first ladder-shaped fixing frame 2, a second ladder-shaped fixing frame 4 and a water-proof steel plate 3; the first ladder-shaped fixing frame 2 and the second ladder-shaped fixing frame 4 are respectively fixed on the upper and lower surfaces of the water-stop steel plate 3 and correspond up and down, and the first ladder-shaped fixing frame 2 and the second ladder-shaped fixing frame 4 are perpendicular to the water-stop steel plate 3; the first ladder-shaped fixing frame 2 and the second ladder-shaped fixing frame 2 Ladder-shaped fixing frames 4 ar...
Embodiment 2
[0046] Such as Figure 5 As shown, the present invention also discloses a construction method for leaving a structure with construction joints, specifically, the construction method includes the following steps:
[0047] Step S1, providing a first ladder-shaped fixing frame and a second ladder-shaped fixing frame, and laying expanded metal on both the first ladder-shaped fixing frame and the second ladder-shaped fixing frame.
[0048] Specifically, the above step S1 is specifically:
[0049] Step S11 , providing 2 sets of ladder-shaped fixing frame materials, such as steel bars with a diameter of Φ10, and each set of ladder-shaped fixing frame materials includes 2 main keels and several secondary keels.
[0050]Step S12, processing the ladder-shaped fixing frame, the distance d of the two main keels of the first ladder-shaped fixing frame is determined and set according to the distance from the steel bar at the bottom of the slab to the water-stop steel plate, and the distanc...