Looking for breakthrough ideas for innovation challenges? Try Patsnap Eureka!

Construction process for prestress support in deep foundation pit

A construction technology and prestressing technology, which is applied in foundation structure engineering, sheet pile walls, excavation, etc., can solve problems such as deformation, hidden safety hazards in pipelines, and unsuitable

Inactive Publication Date: 2018-11-13
江苏地基工程有限公司
View PDF5 Cites 10 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0005] 1) It is prone to collapse and deformation of the excavated foundation pit;
[0006] 2) When digging a deep foundation pit, there are often potential safety hazards in adjacent buildings, underground structures and pipelines;
[0007] 3) The traditional underground diaphragm wall construction method requires large investment, low safety factor, and high construction noise. It requires a wide construction site and is not suitable for construction in urban centers; in traditional deep foundation pits supported by reinforced concrete When the concrete support construction is completed and the curing strength reaches the design requirement value, the soil can be excavated. There is no intersection between the support construction and the earthwork excavation process

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Construction process for prestress support in deep foundation pit
  • Construction process for prestress support in deep foundation pit
  • Construction process for prestress support in deep foundation pit

Examples

Experimental program
Comparison scheme
Effect test

Embodiment

[0090] Example: such as figure 1 As shown, the construction technology of the prestressed support in the deep foundation pit specifically includes the following steps:

[0091] (1) Clean up the site and set out the construction line: clean up the site, and each pile position should be positioned and set out with theodolite and steel tape according to the design requirements;

[0092] (2) Construction preparation: Prepare the required materials and enter the site in batches, and then enter the site after overhauling and maintaining the required mechanical equipment to ensure good performance of the mechanical equipment;

[0093] (3) Constructing the enclosure project: the enclosure method adopts three-axis mixing pile water stop, bored cast-in-situ pile, biaxial mixing pile, reinforced anchor pile and anchor shotcrete, and double-split waist beam to apply prestress; among them, the order is first Connecting and interspersing construction of three-axis mixing piles for water-st...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

PropertyMeasurementUnit
Compressive strengthaaaaaaaaaa
Strengthaaaaaaaaaa
Login to View More

Abstract

The invention relates to a construction process for a prestress support in a deep foundation pit. The construction process specifically comprises the following steps: (1) cleaning a site and constructing and paying off; (2) construction preparation; and (3) constructing enclosure engineering: a prestress is applied in an enclosure mode by means of triaxial stirring pile water sealing, a cast-in-situ bored pile, a biaxial stirring pile, a stiffening anchor rod pile, anchor spraying and a semi-detached waist rail, wherein the step (3) specifically comprises the following steps: sequentially joining and alternately performing triaxial stirring pile water sealing, cast-in-situ bored pile enclosing and biaxial stirring pile matched with earthwork excavation and transportation; firstly, performing construction of the cast-in-situ bored pile, wherein two stirring pile drivers move in opposite directions to reduce construction cold joints, and 3-5 days after construction of the biaxial stirring piles, following up and inputting the mixture into a drilling machine for performing construction of the cast-in-situ bored pile; after construction of the cast-in-situ bored pile, excavating earthwork, and then continuously excavating earthwork after constructing the stiffening anchor rod pile, and performing anchor spraying and the semi-detached waist rail; and repeating the construction flowsin the steps till integral construction of a to-be-constructed super deep foundation pit is finished. The construction process efficiency is high, the safety of the foundation pit is ensured, and theconstruction period is shortened.

Description

technical field [0001] The invention relates to the technical field of building construction, to the technical field of deep foundation pit excavation construction, and in particular to a construction technique for prestressed support in deep foundation pits. Background technique [0002] With the development of economy and society, human beings have more and more demands on the construction of high-rise buildings and long-span bridges. Deep development. Ultra-tall buildings will inevitably require ultra-deep foundation pits as a guarantee. [0003] At present, the support engineering of deep foundation pit has become an important sub-item of high-rise building construction engineering. Since the earthwork of the foundation pit has not been excavated, the foundation pit support construction is developed in a completely concealed and semi-concealed state. Technology is heavily and widely studied in the engineering community. Especially in the construction in the central ar...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
IPC IPC(8): E02D17/02E02D17/04E02D5/18E02D19/18E02D5/46E02D5/76
CPCE02D5/187E02D5/46E02D5/76E02D17/02E02D17/04E02D19/18
Inventor 陈家冬汪小健吴亮尚学伟周曙东周芳张亮周浩达范翔
Owner 江苏地基工程有限公司
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Patsnap Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Patsnap Eureka Blog
Learn More
PatSnap group products