Unlock instant, AI-driven research and patent intelligence for your innovation.

A kind of hard ground steel pipe pile and its construction method

A hard ground and construction method technology, applied in the direction of sheet pile walls, foundation structure engineering, construction, etc., can solve the problem that it is difficult to accurately ensure the alignment of the bottom of the steel pipe pile, it is difficult to control the construction accuracy of the steel pipe pile, and the insertion of the steel pipe pile is difficult. Depth is difficult to control and other issues, to achieve good support reliability, shorten the construction period, improve the effect of construction quality

Active Publication Date: 2021-05-14
CHINA CONSTR FIRST BUILDING GRP CORP LTD
View PDF5 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0004] For the current steel trestle structure, it mainly includes pier piles and beams arranged on the pier piles. The beam body is usually spliced ​​by several Bailey sheets, and the pier piles are usually steel pipe piles. During construction, It is necessary to drive steel pipe piles into the soil layer, and the length of the steel pipe piles entering the soil layer must reach the design length. However, in actual construction, when the steel pipe piles are under hard strata such as sand and pebbles, it is difficult for steel pipe piles to continue. As a result, the insertion depth of steel pipe piles is not enough. In order to ensure the reliability of steel pipe pile support, the current common practice is to first use steel pipes with larger diameters to set them around the design position of steel pipe piles, and then sand and pebbles inside the steel pipes Drill holes on the upper layer, then pour concrete in the drill holes, and insert steel pipe piles into the concrete before the initial setting of the concrete. Although such a steel pipe pile structure can be relatively stable, it needs to install larger steel pipes first, and then place a larger steel pipe pile in the concrete. The operation of drilling, pouring concrete and inserting steel pipe piles in the large steel pipes, on the one hand, involves many construction procedures for installation and removal, which greatly increases the construction cost and construction period, and, because the steel pipe piles are inserted in It is difficult to accurately ensure the alignment of the bottom of the steel pipe pile, so it is difficult to control the construction accuracy of the steel pipe pile; on the other hand, it is difficult to control the insertion depth of the steel pipe pile when the steel pipe pile is inserted before the initial setting of the concrete. Prone to problems such as insertion too deep

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • A kind of hard ground steel pipe pile and its construction method
  • A kind of hard ground steel pipe pile and its construction method
  • A kind of hard ground steel pipe pile and its construction method

Examples

Experimental program
Comparison scheme
Effect test

Embodiment 1

[0082] Example 1, such as Figure 1-9 as shown,

[0083] A steel pipe pile on a hard ground, comprising at least two steel pipes 1, the bottom of the steel pipes 1 is in contact with a hard ground 2, and a drill hole is provided on the hard ground 2 corresponding to the internal space of the steel pipe 1, and the drill holes Concrete is poured into the hole, and the concrete is filled with the borehole and continues to extend upwards, so that the part of the concrete forming the column is located in the steel pipe 1 .

[0084] During the construction of the steel pipe pile on hard ground in this embodiment, when the steel pipe 1 sinks until the hard ground 2 cannot sink further, a drilling rig is used to drill a hole, and then concrete is poured into the borehole, and the concrete is filled to the brim. After drilling, the pouring is continued so that part of the hardened concrete column 4 is located in the drilled hole and a part is located in the steel pipe 1. In this way, ...

Embodiment 2

[0099] Example 2, such as Figure 1-9 Shown:

[0100] A construction method for steel pipe piles in hard ground, comprising the following steps:

[0101] a. Hoisting: hoist the steel pipe 1 to the design position with a hoisting device;

[0102] b. Sinking: Use a vibrating hammer to hammer the steel pipe 1, so that the steel pipe 1 is inserted into the soil layer until the lower end of the steel pipe 1 reaches the hard layer 2;

[0103] c. Drilling: Drilling equipment is used to drill the hard stratum 2 below the inner space of the steel pipe 1, and the drilling depth is greater than or equal to the design depth of the steel pipe 1 inserted into the stratum;

[0104] d. Concrete pouring: Pour concrete into the borehole formed in step c, and continue pouring after the concrete is filled with the borehole, so that the concrete is poured into the steel pipe 1 and reaches the design height.

[0105] Using the construction method of this embodiment, on the premise of ensuring th...

Embodiment 3

[0118] Example 3, as Figure 1-9 shown,

[0119] A steel trestle includes several steel pipe piles and beam bodies 10 arranged on the steel pipe piles. The bridge abutment 11 is provided with a support profile 12 for supporting the end of the beam body 10 on the bridge abutment 11 .

[0120] In the steel trestle of this embodiment, the supporting profiles 12 are arranged on the abutments 11 to increase the force bearing area of ​​the abutments 11, thereby improving the reliability of the support of the abutments 11, and the support height can be adjusted by selecting profiles of appropriate sizes, Further realize, the adjustment of the height of the beam body 10 at the bridge platform 11;

[0121] In particular, the connection strength between the beam body 10 and the supporting profile 12 is less than the strength of the beam body 10 being damaged by impact. When the beam body 10 is subjected to a large impact force, the beam body 10 is separated from the profile and overla...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The present invention relates to the field of building construction, in particular to a steel pipe pile for hard ground and a construction method thereof. The steel pipe pile for hard ground includes at least two steel pipes, the bottom of the steel pipes is in contact with the hard ground, and the The hard ground corresponding to the inner space of the steel pipe is provided with a borehole, and concrete is poured into the borehole. Inside the steel pipe. For the steel pipe pile in hard stratum of the present application, during construction, when the steel pipe sinks until the hard stratum cannot sink further, a drilling rig is used to drill the hole, and then concrete is poured into the borehole and the steel pipe. Compared with the traditional In terms of method, the construction method is simple, which not only greatly simplifies the construction process, but also can coordinate and control the structural strength and stability of steel pipe piles through the depth of drilling and the height of concrete inside the steel pipe pile, so as to ensure the stability of steel pipe piles and reliability.

Description

technical field [0001] The invention relates to the field of building construction, in particular to a hard layer steel pipe pile and a construction method thereof. Background technique [0002] In the field of construction engineering technology, when a river-crossing project is involved, if the river does not allow large ships to carry equipment or enter the site as auxiliary construction equipment, it is usually necessary to set up auxiliary construction channels on the river to ensure the smooth progress of the construction. . [0003] The current auxiliary construction channels usually include pontoon bridges, steel trestle bridges and artificial islands, etc. The corresponding structures should be selected according to different actual construction situations. For example, for the turbulent water flow, artificial island construction and pontoon bridge structures should not be used as auxiliary construction channels. River, steel trestle structure has become a more com...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Patents(China)
IPC IPC(8): E02D5/38
CPCE02D5/38
Inventor 谢全鸿雍翔张效铭蒙文武周杰杨闯李臣陈东川刘瑞斌漆涛何煜民
Owner CHINA CONSTR FIRST BUILDING GRP CORP LTD