A kind of hard ground steel pipe pile and its construction method
A hard ground and construction method technology, applied in the direction of sheet pile walls, foundation structure engineering, construction, etc., can solve the problem that it is difficult to accurately ensure the alignment of the bottom of the steel pipe pile, it is difficult to control the construction accuracy of the steel pipe pile, and the insertion of the steel pipe pile is difficult. Depth is difficult to control and other issues, to achieve good support reliability, shorten the construction period, improve the effect of construction quality
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0082] Example 1, such as Figure 1-9 as shown,
[0083] A steel pipe pile on a hard ground, comprising at least two steel pipes 1, the bottom of the steel pipes 1 is in contact with a hard ground 2, and a drill hole is provided on the hard ground 2 corresponding to the internal space of the steel pipe 1, and the drill holes Concrete is poured into the hole, and the concrete is filled with the borehole and continues to extend upwards, so that the part of the concrete forming the column is located in the steel pipe 1 .
[0084] During the construction of the steel pipe pile on hard ground in this embodiment, when the steel pipe 1 sinks until the hard ground 2 cannot sink further, a drilling rig is used to drill a hole, and then concrete is poured into the borehole, and the concrete is filled to the brim. After drilling, the pouring is continued so that part of the hardened concrete column 4 is located in the drilled hole and a part is located in the steel pipe 1. In this way, ...
Embodiment 2
[0099] Example 2, such as Figure 1-9 Shown:
[0100] A construction method for steel pipe piles in hard ground, comprising the following steps:
[0101] a. Hoisting: hoist the steel pipe 1 to the design position with a hoisting device;
[0102] b. Sinking: Use a vibrating hammer to hammer the steel pipe 1, so that the steel pipe 1 is inserted into the soil layer until the lower end of the steel pipe 1 reaches the hard layer 2;
[0103] c. Drilling: Drilling equipment is used to drill the hard stratum 2 below the inner space of the steel pipe 1, and the drilling depth is greater than or equal to the design depth of the steel pipe 1 inserted into the stratum;
[0104] d. Concrete pouring: Pour concrete into the borehole formed in step c, and continue pouring after the concrete is filled with the borehole, so that the concrete is poured into the steel pipe 1 and reaches the design height.
[0105] Using the construction method of this embodiment, on the premise of ensuring th...
Embodiment 3
[0118] Example 3, as Figure 1-9 shown,
[0119] A steel trestle includes several steel pipe piles and beam bodies 10 arranged on the steel pipe piles. The bridge abutment 11 is provided with a support profile 12 for supporting the end of the beam body 10 on the bridge abutment 11 .
[0120] In the steel trestle of this embodiment, the supporting profiles 12 are arranged on the abutments 11 to increase the force bearing area of the abutments 11, thereby improving the reliability of the support of the abutments 11, and the support height can be adjusted by selecting profiles of appropriate sizes, Further realize, the adjustment of the height of the beam body 10 at the bridge platform 11;
[0121] In particular, the connection strength between the beam body 10 and the supporting profile 12 is less than the strength of the beam body 10 being damaged by impact. When the beam body 10 is subjected to a large impact force, the beam body 10 is separated from the profile and overla...