High-strength road surface and construction process thereof
A high-strength, construction method technology, applied in the direction of roads, roads, pavement details, etc., can solve the problems of bumps or pits, slippage, etc. on the road surface, and achieve the effect of reducing the possibility of bumps or pits
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0043] like figure 1 As shown, a high-strength pavement includes a soil layer 1, a graded crushed stone layer 2, a concrete layer 3 and an asphalt layer 4 from bottom to top.
[0044] like figure 2 As shown, the concrete layer 3 is laid with steel mesh 5 along the horizontal direction, and the crack resistance of the concrete layer 3 is improved through the steel mesh 5 . Each node of the reinforcement mesh 5 is bound with a vertically oriented vertical steel bar 6, the lower end of the vertical steel bar 6 is inserted into the graded crushed stone layer 2, and the upper end of the vertical steel bar 6 passes through the concrete layer 3, and each There is a distance of 10 cm between the uppermost ends of the vertical steel bars 6 and the upper end surface of the concrete layer 3 .
[0045] like figure 2 and image 3 As shown, the vertical reinforcing bars 6 arranged on the same straight line along the width direction of the road are divided into two by taking the center...
Embodiment 2
[0048] A construction method for the above-mentioned high-strength pavement, comprising:
[0049] Step 1. Laying graded gravel layer 2
[0050] Pour and level the fine crushed stones above the soil layer 1, then lay and level the crushed stones with slightly larger particles, and repeat the above steps to lay the graded crushed stone layer 2.
[0051] Step 2. Build the steel frame
[0052] Build a horizontal reinforcement mesh 5 above the graded crushed stone layer 2, and bind vertically oriented vertical reinforcement bars 6 on each node of the reinforcement mesh 5, the lower end of the vertical reinforcement bars 6 is inserted into the graded crushed stone layer 2 Inside, and ensure that the upper ends of the vertical steel bars 6 are flush. The vertical steel bars 6 arranged on the same straight line along the width direction of the road are divided into two with the centerline of the road as the dividing line as two steel bar groups. The position of the side is pre-ground...