Construction method for pore forming in artificial rockfill layer
Patent Information
- Authority / Receiving Office
- CN ยท China
- Current Assignee / Owner
- SHANGHAI BAOYE GRP CORP
- Publication Date
- 2019-02-26
Abstract
Description
technical field
[0001] The invention relates to a construction method for forming holes in an artificial rock filling layer. Background technique
[0002] With the rapid development of urban construction, coastal cities continue to carry out large-scale land reclamation. Most of the original land reclamation sites belong to coastal tidal landforms. The artificial landfill materials are mainly composed of granite blocks, and the diameter of the blocks is generally 20-80cm. , with a maximum diameter of more than 1m, filled with gravel, breccia and cohesive soil, and the layer thickness is uneven. When carrying out the construction of deep foundation pit support piles in the reclamation area, it is often encountered that the rock filling layer is difficult to pass through, and the hole is difficult to form, which brings troubles to the support pile construction and affects the normal construction of the building. , Increase the cost of construction operations and reduce the ef...