A construction method and untreated technology, applied in earthwork drilling, shaft lining, tunnel lining, etc., can solve problems such as lowering, ground subsidence, and endangering safety, and achieve the effects of increasing specific gravity and viscosity, improving performance, and reducing difficulty

Active Publication Date: 2019-08-16
URBAN MASS TRANSIT ENG CO LTD OF CHINA RAILWAY 11TH BUREAU GRP
View PDF12 Cites 5 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

Since the shield earth silo needs to be balanced with the earth pressure, if the shield tunnel encounters untreated karst caves or cracks during construction, the pressure of the earth silo will decrease, and even cause the ground to collapse, seriously endangering the safety of the excavation process.

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Construction method for sudden encounter of untreated karst caves or fractures during shield tunneling
  • Construction method for sudden encounter of untreated karst caves or fractures during shield tunneling
  • Construction method for sudden encounter of untreated karst caves or fractures during shield tunneling

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0036] Below in conjunction with embodiment the present invention is further described.

[0037] The embodiment is for a shield section of the Guangzhou Metro, which is constructed using the shield method. The length of the left line of the section is 1098.87m, and the length of the right line of the section is 1099.188m. The buried depth is about 13.5-19.8m. The landform along this interval is mainly the alluvial plain of the Pearl River Delta, the terrain is relatively flat, the ground elevation is about 6.0-10.0m, and the Quaternary alluvial soil layer and sand layer are developed. The formations mainly traversed in this interval include silt-fine sand, medium-coarse sand, gravel sand, silty clay (flow plastic ~ soft plastic), silty clay (plastic), silty soil, limestone residual soil (soft plastic), limestone micro-weathered strata and soil caves, caves . In the early stage of shield construction, 5m / hole was re-intensively surveyed, and the penetration rate was fou...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

The invention provides a construction method for sudden encounter of untreated karst caves or fractures during shield tunneling. In the shield tunneling process, when the earth silo pressure drops orthe amount of excavated earth decreases, blended thick mud is injected into an earth silo, and then segments with reserved grouting holes are assembled in the tunneling process until shield parametersreturn to be normal, after the assembly is completed, through drilling holes in the segment reserved grouting hole positions in a pressure-loss area of the earth silo, the positions of the karst caves or fractures are detected, and check valves are installed at the hole positions, communicating with the karst caves or fractures, polyurethane slurry is injected, and after grouting is completed, the grouting position is subjected to hole expansion, sleeve valve steel pipes are buried, and cement slurry is injected into the water leakage position; and meanwhile, the ground is monitored at the pressure-loss position of the earth silo, and in areas with large settlement, WSS grouting reinforcement is adopted. According to the construction method, the thick mud is used for treating the karst caves, then the karst cave fractures are plugged by injecting polyurethane and the cement slurry and cooperating with the ground WSS grouting stratum reinforcement, and the problem of shield tunneling encountering untreated karst caves is effectively solved.

Description

technical field [0001] The invention belongs to the field of urban rail transit engineering, and specifically aims at a construction method for shield tunneling when it encounters untreated karst caves or cracks, so as to ensure that the shield tunnel can pass through the karst cave development area normally and ensure the safety of shield tunneling. Background technique [0002] As my country's infrastructure construction has entered a white-hot stage, urban rail transit construction has also followed the wave of infrastructure construction to continue to develop rapidly, and shield construction is also playing an increasingly important role in the subway construction process. In southern my country, Yunnan, Guangxi, Guangdong, Guizhou, Sichuan and other regions are greatly affected by karst, and it is inevitable that shield tunnels will pass through karst cave development areas. The construction of tunnels brings great risks. The development of karst caves not only serious...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
Patent Type & Authority Applications(China)
IPC IPC(8): E21D11/10E21D9/06E21B33/13E21D11/08
CPCE21B33/13E21D9/06E21D11/08E21D11/105
Inventor 阳紫东李应姣杨梅张桥刘晓杰梅灿刘铮
Owner URBAN MASS TRANSIT ENG CO LTD OF CHINA RAILWAY 11TH BUREAU GRP
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products