[0029] Described construction method comprises the steps:
[0030] Step 1, ground surface reinforcement at the entrance section: level the ground in the grouting area, place a drilling rig on the ground after leveling and drill the hole to the designed depth, and place the grouting pipe 2 in the drilled hole; In the vertical reinforcement method, the grouting grout is evenly injected into the soil from the grouting pipe 2 through the grouting pump and the grouting pipe, and the moisture and gas between the loose rock mass particles are driven away by filling and infiltration; the grouting grout Prioritize the use of cement slurry; check the strength and bearing capacity of the grouting body after construction;
[0031] Step 2. Slope protection at the entrance of the cave: use an excavator to excavate the slope surface 3, manually repair the slope surface 3, and use a concrete sprayer to spray the concrete; after the sprayed concrete reaches the design strength, the anchor cabl...