Double-side Pilot Excavation Method for Tunnel Excavation

A double-side pilot pit and tunnel excavation technology, which is applied in tunnels, tunnel linings, earthwork drilling and mining, etc., can solve problems affecting construction progress, large spans, easy collapse, etc., to reduce longitudinal thrust, maintain stability, reduce deformation effect

Active Publication Date: 2021-06-29
ROAD & BRIDGE SOUTH CHINA EINGINEERING CO LTD
View PDF9 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

However, shallow-buried and underground excavated large-section gradient tunnels for urban railways have large spans and complex construction procedures. It is difficult to mass-produce the initial support of the gradient section, and the construction efficiency is low, which seriously affects the construction progress, especially in weak surrounding rocks. Surface subsidence and The horizontal displacement of the gradient section is difficult to control, and the construction is extremely difficult
Shallow-buried and underground excavated large-section gradient tunnels for urban subways, especially V-level shallow buried sections, soil surrounding rock ends, or entrance sections with severe weathering and fracture (S-Va), have poor strength and stability, and are prone to collapse during excavation

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Double-side Pilot Excavation Method for Tunnel Excavation
  • Double-side Pilot Excavation Method for Tunnel Excavation
  • Double-side Pilot Excavation Method for Tunnel Excavation

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0031] Embodiments of the present application are described in detail below, examples of which are shown in the drawings, wherein the same or similar reference numerals denote the same or similar elements or elements having the same or similar functions throughout. The embodiments described below by referring to the figures are exemplary only for explaining the present application, and are not construed as limiting the present application.

[0032] See Figure 1 to Figure 4 , the present application relates to a double-side-wall pilot-pit excavation method for tunnel excavation, in which the tunnel end face is divided into a pilot-pit excavation area, a core soil excavation area 3 and a tunnel bottom excavation area 4, The excavation area of ​​the pilot pit is divided into two excavation areas located around the core soil excavation area 3, and weak blasting or mechanical excavation are adopted, so that the tunnel has good structural stability during the excavation process, wh...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The application provides a double-side pilot pit type excavation method for tunnel excavation, which includes the following steps: (1) dividing the tunnel section into pilot pit excavation area, core soil excavation area and tunnel bottom excavation (2) In the case of advanced support, excavate the excavation area of ​​the pilot pit; (3) In the case of advanced support of the side wall of the pilot pit and the main tunnel, excavate the core in stages from the top of the tunnel to the bottom of the tunnel (4) Excavate the excavation area at the bottom of the tunnel, and erect support to form a ring with the existing support; (5) Remove the temporary support and pour the main tunnel invert; (6) Lay waterproof boards, using The formwork trolley is used for secondary lining; (7) Repeat the above steps until the tunnel is penetrated. The pilot pit excavation area is constructed before the core soil excavation area, and the soil in the core soil excavation area is used as support to reduce the longitudinal thrust of the tunnel face soil and prevent the collapse of the surrounding rock vault, effectively reducing tunnel The sinking of the primary support vault and the convergence of the headroom level ensure construction safety.

Description

technical field [0001] The present application relates to the field of railway tunnel construction, in particular to a double-side pilot-pit excavation method for tunnel excavation. Background technique [0002] In recent years, my country's urban railways have developed rapidly, and the number and mileage of construction have increased year by year, and great achievements have been made. However, shallow-buried and underground excavated large-section gradient tunnels for urban railways have large spans and complex construction procedures. It is difficult to mass-produce the initial support of the gradient section, and the construction efficiency is low, which seriously affects the construction progress, especially in weak surrounding rocks. Surface subsidence and The horizontal displacement of the gradient section is difficult to control, and the construction is extremely difficult. Shallow-buried and underground excavated large-section gradient tunnels for urban subways, ...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Patents(China)
IPC IPC(8): E21D9/00E21D11/00E21D11/10E21D11/38F42D3/04E21D9/04
CPCE21D9/00E21D9/006E21D9/04E21D11/006E21D11/10E21D11/38
Inventor 吴建峰卢卓杨卫平郑云青刘怀刚袁小宁高世强肖向荣陈勇丰韩春鹏陈振宇唐代新
Owner ROAD & BRIDGE SOUTH CHINA EINGINEERING CO LTD