A tunneling method for mine cross-section cutting and tunneling
A cross-section and roadway technology, which is used in ground mining, earth-moving drilling, underground mining, etc., can solve the problems such as the inability to achieve rapid penetration of the incision and the return air along the groove, reduce the safety of the driving operation, and reduce the driving speed. The effect of cutting eye maintenance works, shortening the construction period, and ensuring the output
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Examples
Embodiment 1
[0047] A roadway excavation method for mine cross-section cuts, wherein the cuts are 9201 cuts, the total width of the 9201 cuts is 7m, the length is 150m, and the height is 3m, and the excavation of the 9201 cuts adopts the secondary expansion roadway excavation process , the method of excavation and falling coal is all the cutting method of a single roadheader. First, the width of the roadway is reduced, and the width of 3.5 meters is 3.5 meters. The width of the roadway is 7m and the length is 150m. First, reduce the width of the roadway and excavate 150 meters with a width of 3.5 meters to connect with the return air trough. Safety during operation, and at the same time, after the breakthrough, the use of local fans can be stopped in advance, achieving the effect of energy saving.
[0048] The specific steps are:
[0049] The first step: judge the actual situation of the coal seam in the working face during the early excavation process, and cut the nest groove through the...
Embodiment 2
[0072] A roadway excavation method for mine section cuts, including cuts, the cuts are 9201 cuts, the total width of the 9201 cuts is 7m, the length is 150m, and the height is 3m. The excavation of the 9201 cuts adopts secondary expansion Bangcheng roadway excavation technology, the method of excavation and falling coal is all cut by a single roadheader. First, the width of the roadway is reduced, and the width is 3.5 meters, and the 150-meter tunnel is connected with the return air channel. The roadheader mines the side coal to the design width. The total width of the cutting hole is 7m, and the length is 150m. First, reduce the width of the roadway, and excavate 150 meters with a width of 3.5 meters to connect with the return air trough. The penetration increases the safety during the excavation operation. At the same time, after the penetration, the use of the local ventilator can be stopped in advance to achieve the effect of energy saving.
[0073] It should be noted that...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com