A construction method and concrete technology, which is applied in the direction of construction and building structure, can solve the problems of lagging construction progress, slow construction progress, reducing the bearing capacity and durability of cantilevered slabs, etc., so as to reduce the pressure of the construction period, speed up the construction progress, The effect of reducing post-maintenance costs

Inactive Publication Date: 2020-07-03
CHINA SHANXI SIJIAN GRP
View PDF5 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0002] The upper and lower slabs of the bay window are cast-in-place concrete cantilevered structures. There are two traditional construction methods: one is to pursue the surface construction progress. When using the wall construction, all the upper and lower slabs of the bay window are reserved for the horizontal steel bars of the cantilever slab, and the concrete pouring of the wall is completed. Afterwards, the cantilevered components are poured separately. In this construction process, the positions of the pre-embedded steel bars on the upper and lower slabs are inaccurate, the secondary construction still has cross operations, the formwork reinforcement is complicated, and the real construction progress is lagging behind.
The second is to construct synchronously with the main structure of the same floor. Due to the cross-operation here, the construction progress is slow; and the overhanging steel bars of the lower bay window panels are seriously trampled, resulting in too large a protective layer of steel bars, which reduces the bearing capacity and capacity of the cantilevered slabs. Quality defects such as durability, cross-sectional size deviation, concrete honeycomb pitting, insufficient arching, and poor flatness

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Building facade concrete bay window board construction method

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0020] The following will clearly and completely describe the technical solutions in the embodiments of the present invention with reference to the accompanying drawings in the embodiments of the present invention. Obviously, the described embodiments are only some, not all, embodiments of the present invention. Based on the embodiments of the present invention, all other embodiments obtained by persons of ordinary skill in the art without making creative efforts belong to the protection scope of the present invention.

[0021] Such as figure 1 Shown, a kind of construction method of building exterior concrete bay window panel comprises the following steps:

[0022] S1. Measure and set out the wires, and bind the steel bars according to the design requirements;

[0023] S2. Set up the formwork for the upper bay window panel, and reserve the reinforcement bars for the lower bay window panel;

[0024] S3. Pouring concrete and curing according to design requirements;

[0025] ...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention relates to the technical field of bay window board building construction, in particular to a building facade concrete bay window board construction method. The method comprises the stepsof S1, performing surveying and setting out, wherein reinforcing steel bars are bound according to the design requirement; S2, erecting a formwork on an upper bay window board, and reserving lower bay window board reinforcing steel bars; S3, pouring concrete according to the design requirement for maintenance; S4, after the concrete meets the requirement for formwork disassembling, performing formwork disassembling; S5, performing secondary construction on a lower bay window board; S6, after construction of the lower bay window board is completed, performing acceptance inspection. When the body structure is constructed, the building facade upper bay window board and floors are synchronously constructed, reinforcing steel bars are reserved for the lower bay window board, and construction is performed after the formwork of the same layer is disassembled. According to the method, the construction progress can be accelerated, the quality of each procedure is effectively controlled, a project can be excellent at a time, the later maintenance cost is greatly lowered, and the pressure of the time limit for the project is relieved. The method is mainly applied to the aspect of building facade bay window board construction.

Description

technical field [0001] The invention relates to the technical field of building construction of bay window panels, and more specifically relates to a construction method for concrete bay window panels on building facades. Background technique [0002] The upper and lower slabs of the bay window are cast-in-place concrete cantilevered structures. There are two traditional construction methods: one is to pursue the surface construction progress. When using the wall construction, all the upper and lower slabs of the bay window are reserved for the horizontal steel bars of the cantilever slab, and the concrete pouring of the wall is completed. Finally, the cantilevered components are poured separately. In this construction process, the positions of the pre-embedded steel bars on the upper and lower slabs are inaccurate, the secondary construction still has cross operations, the formwork reinforcement is complicated, and the real construction progress is lagging behind. The secon...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
IPC IPC(8): E04B1/00
CPCE04B1/00
Inventor 李春红王龙强王亚萍王永刚赵廷帅王晓东侯伟籍跃奎
Owner CHINA SHANXI SIJIAN GRP