Scrap cemented carbide quenching and recycling method
A cemented carbide and waste technology, which is applied in the field of waste cemented carbide recycling, can solve the problems of low purity and yield of cemented carbide, and achieve the effects of less burning loss, high efficiency and good quenching effect.
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0028] (1) Quenching and crushing:
[0029] Put 4.5 kg of waste cemented carbide (cobalt-tungsten alloy) rods into the graphite crucible of the intermediate frequency furnace, adjust the initial power of the intermediate frequency furnace to 3.5kw to start heating, and increase the power by 2kw every 10 minutes, and the alloy is And outside, heating up rapidly, the alloy turns red. Every time the power increases by 2kw, an infrared thermometer is used to measure the temperature on the surface of the cemented carbide. The entire heating process is only 50 minutes, and the temperature reaches about 1300°C required by the quenching process, and is kept at this quenching temperature for 1 hour. For ordinary resistance furnaces, the entire heating process takes 3 hours, and after the temperature reaches the process requirements, it needs to be kept warm for 1 hour. It can be seen that compared with the resistance furnace, the heating efficiency of the intermediate frequency furna...
Embodiment 2
[0043] (1) Quenching and crushing:
[0044] Put 6.2 kg of waste hard alloy (cobalt-tungsten alloy) rods into the graphite crucible of the intermediate frequency furnace, adjust the initial power of the intermediate frequency furnace to 3.5kw to start heating and quenching, and increase the power by 2kw every 8 minutes, the alloy is made of Inside out, the temperature rises rapidly, and the alloy turns red. Every time the power increases by 2kw, an infrared thermometer is used to measure the temperature on the surface of the cemented carbide, and the temperature rises rapidly. The entire heating process is only 40 minutes, and the temperature reaches about 1400°C required by the process, and is kept at this quenching temperature for 2 hours. For ordinary resistance furnaces, the entire heating process takes 3 hours, and after the temperature reaches the process requirements, it needs to be kept warm for 2 hours. It can be seen that compared with the resistance furnace, the he...