Optimization method for capacity calculation of black-start diesel units in thermal power plants and start-up sequence of plant loads
A technology for diesel generator sets and start-up sequences, applied in electrical components, circuit devices, AC network circuits, etc., can solve the problems of optimization, increase in cost, lack of model establishment and simulation verification, etc., and achieve the effect of reducing configuration capacity and reducing cost.
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0024] The present invention will be further described below with reference to the specific drawings and embodiments.
[0025] The embodiment of the present invention proposes an optimization method for the capacity calculation of the black-start diesel unit of the thermal power plant and the start-up sequence of the plant load, which is realized by Matlab / Simulink software; the method includes the following steps:
[0026] Step S1, read the plant load data of the thermal power plant, and add up and calculate the total capacity Se1 of all the plant loads;
[0027] Step S2, using the particle swarm optimization algorithm (PSO) to optimize the start-up sequence of the plant loads, and obtain the total capacity Se2 of the plant loads corresponding to the optimized start-up sequence;
[0028] In this step, the following mathematical model needs to be established:
[0029] Let the starting sequence of n plant loads be F 1 ,F 2 ,...F m ...F n ; The minimum value minSe of the di...