[0035] The present invention will be further described below in conjunction with the examples. The description of the following examples is provided only to aid the understanding of the present invention. It should be pointed out that for those skilled in the art, without departing from the principle of the present invention, some improvements and modifications can be made to the present invention, and these improvements and modifications also fall within the protection scope of the claims of the present invention.
[0036] The construction method of the mud circulation system of the bored pile in complex geological conditions comprises the following steps:
[0037] S1. Weld the bottom end plate 1 61, the supporting steel frame 5 and the bottom end plate 2 62 inside the large-diameter steel pipe pile 1, cut the beam groove 6 on the top of the large-diameter steel pipe pile 1, and the diameter of the large-diameter steel pipe pile 1 2- 4m, wall thickness 15-30mm; the large-dia...