Construction process of large span complex arch roof
A construction technology and large-span technology, applied to roofs, building components, buildings, etc., to achieve the effects of easy assembly, reducing high-altitude operations, and reducing labor intensity
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Examples
Embodiment 1
[0067] The large-span complex arch roof construction technology provided in this embodiment includes the following steps:
[0068] (1) Set up the tire frame directly below the installation position of the floor arch, and assemble the floor arch on the tire frame, and assemble it step by step from low to high.
[0069] (2) Hoisting the first and second arches in the middle.
[0070] (3) The crawler crane lifts the first truss column of the 1st axis and the 18th axis
[0071] 1) Before the truss hoisting operation, the command signal should be unified, and all construction personnel must be familiar with this signal.
[0072] 2) All construction personnel involved in hoisting must be familiar with the project content and hoisting methods.
[0073] 3) During hoisting, the entire site is assigned by a general commander, and the sub-commanders at each post should correctly and quickly implement the orders of the general commander, so as to transmit signals quickly and correctly, ...
Embodiment 2 application example
[0103] The main hall of the International Exchange Center of China Petroleum Equipment Industry Base
[0104]The main hall of the International Exchange Center of China Petroleum Equipment Industry Base is located in the east of Xier Road, Dongying District, Dongying City, Shandong Province, west of Yanshan Road, and north of Naner Road. The building structure is reinforced concrete frame shear wall structure and steel structure, with a total construction area of 52,745㎡ and a curtain wall of about 59,000㎡. The total construction area is 52,745㎡, and the curtain wall is about 59,000㎡. The entrance of the exhibition hall adopts a steel pipe truss structure system, the spacing between truss columns is 9.0m, and the maximum span is 23.0m. The steel truss members are round steel pipes made of Q345B steel, and the steel pipes are directly intersected with welded joints. The trusses are spatial triangular trusses and quadrilateral trusses, and there are support rods between the ...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com