A layout method and technology of reaction columns, applied in chemical instruments and methods, restoration of contaminated soil, contaminated groundwater/leachate treatment, etc., can solve problems such as high cost, difficult construction, large blindness, etc., and achieve reduction Construction cost, effect of improving constructability
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment
[0028] Example: such as Figure 1-6 As shown, the present embodiment relates to a discontinuous PRB reaction column layout method, the method steps are as follows:
[0029] a. Calculate the spacing, thickness, number of rows and height of the reaction column 1;
[0030] B, select the medium reaction material of reaction column 1;
[0031] c. If Figure 5 As shown, according to the calculated spacing, thickness, row number and height of the reaction column 1, the construction is carried out according to the following process:
[0032] (1) Make a plan according to the calculation results, and obtain the coordinates or latitude and longitude of each reaction cylinder;
[0033] (2) According to the longitude, latitude and coordinates of the reaction cylinder, use theodolite to place and locate points;
[0034] (3) Use a professional engineering drilling rig to drill holes, dig multiple wellheads, and fill the tube wells 3 below each wellhead with filter material and form a wel...