Multi-stage purification type grass planting ditch special for green sponge and construction method thereof
A grass-planting ditch and stage purification technology, which is applied to the multi-stage purification grass-planting ditch for green sponge and its construction field, can solve the problems that the grass-planting ditch cannot be purified at the same time, the grass-planting ditch cannot be discharged quickly, and the cost of excessive rainwater is high, so as to prolong the surface runoff The effect of length, quick and easy construction, and simple structure
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0053] like figure 1 and figure 2 As shown, the first filter area includes planting soil layer 15 , sand layer 16 and zeolite layer 17 sequentially from top to bottom, and the base 112 of the baffle plate 11 is buried in the zeolite layer 17 . Rainwater in urban roads according to figure 1 The arrow below indicates that it enters the grass planting ditch, and the water in the infiltration part enters the inside of the baffle plate 11 after being filtered by the above three layers, and finally the relatively clean water flows from the Figure 4 The water collection pipe 22 is shown entering the city drain.
[0054] Further, in a specific embodiment of the present invention, the second filter area includes multiple, and different second filter areas have different particle sizes according to the order in which the water flows through. diameter from thick to thin. Because the water flow in the water flow area has a certain route, along with the flow of the water flow, the wa...
Embodiment 2
[0063] A construction method for a multi-stage purification type grass-planting ditch dedicated to green sponges, comprising the following steps:
[0064] Step 1. Dig a trapezoidal ditch with a wide top and a narrow bottom on both sides of the road in the area to be constructed, clear the bottom and compact it, and install a water collection pipe 22 at the bottom of the ditch near the outflow area 2;
[0065] Step 2: Spread a layer of zeolite on the surface of the tamped ditch bottom, then place the base 112 of the baffle 11 on the zeolite, and use a water stop to adhere the baffle 11 and the baffle 11 to form a water flow channel 1, Then spread a layer of zeolite on the base 112, so that the base 112 of the baffle plate 11 is pressed in the zeolite layer 17; a sand layer 16 is laid on the zeolite foundation, and a water-permeable geotextile is used between the two to separate; the sand layer 16 Lay planting soil layer 15 on the basis to plant turf; form infiltration zone and ...
PUM
Property | Measurement | Unit |
---|---|---|
particle diameter | aaaaa | aaaaa |
particle diameter | aaaaa | aaaaa |
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com