Method for realizing visualization of substation monitoring information acceptance operation based on source end maintenance technology

A technology for substation monitoring and source-side maintenance, applied in information technology support systems, electrical components, circuit devices, etc., can solve the problems of low visibility of substation monitoring information acceptance operations, and difficulty in maintaining point meters of substation telecontrol devices. The effect of maintenance difficulty, improving efficiency and reducing work intensity

Pending Publication Date: 2021-04-13
ZHONGSHAN POWER SUPPLY BUREAU OF GUANGDONG POWER GRID
View PDF5 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0004] In order to solve the problems of low visualization degree of substation monitoring information acceptance operation and difficult maintenance of point tables of substation remote control devices, the present invention provides a method based on source end maintenance technology to realize substation monitoring information acceptance operation visualization method

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Method for realizing visualization of substation monitoring information acceptance operation based on source end maintenance technology
  • Method for realizing visualization of substation monitoring information acceptance operation based on source end maintenance technology

Examples

Experimental program
Comparison scheme
Effect test

Embodiment 1

[0023] Such as Figure 1 to Figure 2 As shown, a method based on the source-end maintenance technology to realize the visualization of substation monitoring information acceptance operation includes the following steps: S1: The source-end maintenance simulation master station establishes a network communication connection with the substation remote control device, and communicates to the substation remote control device through the network interface. Automatically read the telecontrol terminal information, and intelligently convert and analyze the telecontrol terminal information to obtain the necessary information for the source maintenance simulation master station. At the same time, establish a simulation dispatching system that can call the channel information of each simulation master station, and obtain the substation model data and Front-end data source; S2: The simulation dispatching system sends information retrieval instructions and downlink control instructions to th...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention discloses a method for realizing visualization of substation monitoring information acceptance operation based on a source end maintenance technology. The method comprises the following steps: enabling a source end maintenance simulation master station to be in communication connection with a substation telecontrol device, automatically reading telecontrol terminal information, carrying out intelligent conversion analysis to obtain source end maintenance simulation master station necessary information, meanwhile, establishing a simulation scheduling system, and obtaining transformer substation model data and a front-end data source; enabling the simulation scheduling system to send an information calling instruction and a downlink control instruction to the transformer substation telecontrol device, and obtaining simulation master station channel information and addition amount execution information respectively; enabling a monitoring center to integrate the channel information of each simulation master station on the same interface for consistency check of monitoring personnel; and enabling an operator to operate the on-site test device to perform acceptance check, checking the operation result synchronously displayed on the on-site visual terminal, obtaining the next operation instruction, and finally realizing visual acceptance check. According to the invention, the visualization of acceptance operation is realized, the efficiency of point-to-point test operation is improved, and the work intensity is reduced.

Description

technical field [0001] The present invention relates to the technical field of electric power dispatching automation system, and more specifically, relates to a method for realizing visual inspection and acceptance operation of substation monitoring information based on source end maintenance technology. Background technique [0002] At present, the way of substation monitoring information acceptance operation is: in a manual way, point-to-point testing is carried out one by one for each master station. This not only requires the cooperation of personnel from multiple departments, but also uses a manual telephone or walkie-talkie for communication, so the working position is relatively limited. In addition, due to the lack of visualization means, source device information (VER version files, CIM models, SVG graphics files, MAP point table files, etc.) cannot be automatically read or used, resulting in a huge and cumbersome workload for staff to perform signal verification ,...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
IPC IPC(8): H02J13/00
CPCH02J13/00001H02J13/00034Y04S10/16Y04S10/40Y02E60/00
Inventor 李国号李波武天龙汤晓晖钟毅
Owner ZHONGSHAN POWER SUPPLY BUREAU OF GUANGDONG POWER GRID