Water turbine governor parameter optimization method, device and system
An optimization method and a technology for optimizing devices, which are applied in safety devices, multi-objective optimization, machines/engines, etc., can solve the problems that the overshoot and adjustment time cannot be optimized at the same time, so as to suppress ultra-low frequency oscillation and improve dynamic performance Effect
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0050] A kind of water turbine governor parameter optimization method of the present invention, see figure 1 shown, including the following steps:
[0051] Step 1: Based on the Matlab / Simulink simulation platform, build the simulation model of the 2-area system of 4 turbines, see for details figure 2 .
[0052] The generator system consists of governor, prime mover, excitation system and power system stabilizer. Except for the governor and the prime mover, the other parameters directly adopt the parameters of the 4-machine 2-area simulation system in the MATLAB R2017a Simulink platform demo.
[0053] The governor adopts PID model, and its transfer function is:
[0054]
[0055] Among them, K p 、K i and K d represent proportional, integral and differential coefficients respectively; B p Indicates the permanent slip coefficient; T y Indicates the servo system time constant.
[0056] The prime mover adopts a rigid water hammer model, and its transfer function is:
...
Embodiment 2
[0087] Based on the same inventive concept as in Embodiment 1, a water turbine governor parameter optimization device is provided in the embodiment of the present invention, including:
[0088] The acquisition unit is used to acquire an objective function for suppressing ultra-low frequency oscillation of the power system, and the parameters to be optimized in the objective function include proportional, integral and differential parameters of all water turbine governors;
[0089] An optimization unit, configured to optimize all parameters to be optimized based on the objective function and a preset optimization algorithm to obtain a Pareto optimal front;
[0090] The solution unit is used to select the solution with the smallest adjustment time within the acceptable range of overshoot according to the obtained Pareto optimal front as the optimal solution, and use the parameters corresponding to the optimal solution as the parameters to be optimized for the turbine governor th...
Embodiment 3
[0102] An embodiment of the present invention provides a water turbine governor parameter optimization system, including a storage medium and a processor;
[0103] The storage medium is used to store instructions;
[0104] The processor is configured to operate according to the instructions to execute the steps of the method according to any one of Embodiment 1.