Construction method for filling karst cave by using advanced grouting pipe of shield tunneling machine

A technology of advanced grouting and construction method, applied in basic structure engineering, drilling pipe, casing and other directions, can solve the problems of shield machine being wrapped in slurry, affecting the safety of shield construction, and not having construction methods, etc. Cave treatment time, good water-stopping effect and highly targeted effect

Pending Publication Date: 2021-08-17
CHINA RAILWAY 12TH BUREAU GRP +1
View PDF5 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

According to the characteristics of shield construction, geological and hydrological conditions affect the construction safety of shield tunneling, especially when there are construction risks such as karst caves in the geology. Whether there are karst caves in the geology needs to confirm the size and location of the karst caves through detailed survey. Fill the karst cave after confirming the location; due to the characteristics of the exploration work, no detailed survey work has been done in the inconvenient or missing areas on the ground
After the start of the shield tunneling, it was found that the shield tunneling had been pushed into the untreated karst cave group, and the karst caves were in the lower part of the shield body, and there was a construction risk of the shield machine falling. The construction method of using conventional ground filling for karst cave treatment has The construction risk of the shield machine being covered by the slurry, so it does not have the construction method of using conventional cavern treatment

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Construction method for filling karst cave by using advanced grouting pipe of shield tunneling machine

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0026] The following clearly and completely describes the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only some of the embodiments of the present invention, but not all of them. Based on the embodiments of the present invention, all other embodiments obtained by persons of ordinary skill in the art without making creative efforts belong to the protection scope of the present invention.

[0027] Such as figure 1 As shown, a construction method for filling karst caves with advanced grouting pipes of shield machines includes the following steps:

[0028] S1. Transformation of advance grouting pipe of shield machine;

[0029] S2. Selection of grouting equipment;

[0030] S3. Reinforcement treatment of grouting equipment;

[0031] S4, inject thick slurry into the soil bin, and control the pressure to 2.5bar;

[0032] S5. Phosphoric acid water glass double liquid slurry is injected around the shield body;

[0033] S6...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

The invention relates to the technical field of tunnel engineering construction, in particular to a construction method for filling a karst cave by using an advanced grouting pipe of a shield tunneling machine. The construction method comprises the following steps that S1, the advanced grouting pipe of the shield tunneling machine is transformed; S2, grouting equipment is selected and used; S3, reinforcement treatment of the grouting equipment is conducted; S4, thick slurry is injected into a soil bin, and the pressure is controlled to be 2.5 bar; S5, phosphoric acid water glass double-liquid slurry is injected into the periphery of a shield body; S6, a drill rod of a drilling machine drills through the advanced grouting pipe; S7, the drilling rod of the drilling machine enters a preset position, and grouting filling is conducted; and S8, the grouting effect is monitored according to the pressure change. The method is compact in pressure maintaining, higher in efficiency and low in construction cost, and has safety and economical efficiency.

Description

technical field [0001] The invention relates to the technical field of tunnel engineering construction, and more specifically relates to a construction method for filling karst caves with advanced grouting pipes of a shield machine. Background technique [0002] With the rapid development of urbanization, life problems such as traffic congestion follow. Therefore, the rapid construction of urban rail transit, shield tunneling is widely used in subway construction due to its safety, efficiency, economy and efficiency. According to the characteristics of shield construction, geological and hydrological conditions affect the construction safety of shield tunneling, especially when there are construction risks such as karst caves in the geology, whether there are karst caves in the geology needs to confirm the size and location of the karst caves through detailed survey. After the site and location are confirmed, the caves will be filled; due to the characteristics of the explor...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
Patent Type & Authority Applications(China)
IPC IPC(8): E21D9/06E02D3/12E21B7/04E21B33/13E21B34/06E21B17/02
CPCE21D9/001E21D9/0642E21D9/0671E21B7/04E21B33/13E21B34/06E21B17/02
Inventor 李鹏飞李自力郭波武鑫星崔军华
Owner CHINA RAILWAY 12TH BUREAU GRP
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products