Prefabricated pavement slab connecting structure based on tongue-and-groove bent bolt connection and installation method
An installation method and a prefabricated road technology are applied to pavements, roads, roads and other directions paved with prefabricated blocks, which can solve the problems of complicated road surface layer processes, long concrete curing time, and inability to meet rapid construction, and achieve good economical results. Benefits and social benefits, fast construction, simple connection structure
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0025] see Figure 1~3 , the prefabricated road panel connection structure based on tongue-and-groove bolt connection, including a precast concrete road panel 1, a convex groove 2, a concave groove 3, a reserved installation groove 4, a reserved hole 5 and a curved bolt 6; the precast concrete The four sides of the road panel 1 are arranged with concave grooves 2 and convex grooves 3, and the precast concrete road panel 1 is symmetrically provided with reserved installation grooves 4 and reserved channels 5, and the upper surface of the precast concrete road panel 1 is provided with four hoisting The grouting hole 10; the precast concrete pavement 1 is fixed by the socket connection of the convex groove 2, the concave groove 3 and the bent bolt 6; the precast concrete pavement 1 is prefabricated by light inorganic materials.
[0026] In the embodiment of the present invention, the prefabricated concrete pavement 1 is manufactured by factory prefabrication, and the groove 2, th...
Embodiment 2
[0032] The installation method of the prefabricated road panel connection structure based on the tongue-and-groove bolt connection, the installation method includes the following steps:
[0033] 1) Complete the construction of the base course of the airport road, and ensure that the airport has a certain strength, rigidity and flatness, so as to meet the assembly construction requirements of the precast concrete road slab 1 of the subsequent road;
[0034] 2) Base-level positioning and setting out. According to the overall division of the working surface, each working surface determines the positioning of the starting plate respectively, and places a positioning line at a certain distance to prevent the accumulated error of the plate from being too large;
[0035] 3) For the laying of the precast concrete pavement slab 1, the component slabs prepared in advance are accurately placed on the starting slab position through the hoisting equipment, and the subsequent slabs are laid ...