Method for quickly installing section steel beam plate under top-down cover-excavation

A technology of cover-excavation reverse operation and installation method, which is applied in the field of steel plate installation and steel beam, which can solve the problems of thick steel plate, difficulty in on-site assembly, and high welding requirements, so as to facilitate installation and adjustment, and improve construction efficiency and quality.

Pending Publication Date: 2021-09-03
THE FIFTH ENG CO LTD OF CHINA TIESIJU CIVIL ENG GRP +2
View PDF11 Cites 1 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0003] However, during the construction process of installing the steel girders and slabs by excavating the cover of the underground structure, the steel columns and beams below the cover slab cannot be constructed by conventional hoisting machinery and hoisting methods, and the steel beams and columns are constructed in sections, making it difficult to assemble on site At the same time, because the thickness of the steel plate is thick and the welding requirements are high, whether it is a steel beam or a steel column, how to ensure the accuracy of its positioning can smoothly meet the requirements of the specification and how to ensure the safety of the steel column from flat to standing. Difficulties and key points in the installation process of beams and slabs

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Method for quickly installing section steel beam plate under top-down cover-excavation
  • Method for quickly installing section steel beam plate under top-down cover-excavation
  • Method for quickly installing section steel beam plate under top-down cover-excavation

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0061] The present invention is further described below with reference to the drawings, and the scope of the invention is not limited to the following:

[0062] like Figure 1 ~ 8 As shown, a rapid installation method of the type steel beam under the cover retrorefold conditions, including the following steps;

[0063] Step S1: Construction preparation. Construction preparation includes through design, understanding of engineering and main design intentions, engineering site conditions and positioning conditions, main building interrelations and axis size, high grounds on the ground, and design for measurement accuracy requirements. Through the drawings, the calculation of the discharge data is performed, and the calculation of data is determined by different people to use different methods, and the calibration is performed to reduce the appearance of accidental errors. Understand the construction site layout and construction progress in advance, ensure the deepening, processing, t...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

PropertyMeasurementUnit
Lengthaaaaaaaaaa
Verticalityaaaaaaaaaa
Login to view more

Abstract

The invention discloses a method for quickly installing a section steel beam plate under top-down cover-excavation. The method comprises the following steps: preparing for construction; 1) excavating a foundation pit of a top plate to a designed elevation, 2) pouring concrete on a cushion layer, 3) enabling entering of a section steel beam, (4) conducting temporary support installation of the top plate section steel beam; (5) hoisting and positioning the top plate section steel beam; (6) installing and rechecking the top plate section steel beam; (7) binding cover plate reinforcing steel bar and pouring concrete; 8) excavating the foundation pit on a negative one floor, 9) positioning and hoisting a mid-slab section steel beam slab, 10) installing and rechecking the mid-slab section steel beam slab, 11) binding a middle slab reinforcing steel bar and pouring concrete, 12) constructing a side wall section steel column, and 13) completing installation of each middle slab section steel beam in sequence. Beneficial effects are as follows: the method has a compact structure, relieves working intensity of workers, and improves filtrate filtering efficiency and extraction efficiency of medicine components.

Description

Technical field [0001] The present invention relates to the technical field of steel beams, steel sheets, in particular, a rapid mounting method of the type steel beam under a cover retrofold. Background technique [0002] The steel concrete combination structure is an independent structure in which steel is buried in reinforced concrete. Since the addition of type steel has good strength and ductility, it is better than the traditional reinforced concrete structure, and the seismic performance is better. At the same time, domestic and foreign trials have shown that the steel concrete combination structure has good hysteresis and energy consumption under low cycle, and has the characteristics of local stability of good structural and good structures compared to the steel structure. Therefore, in my country's high-level and large underground The development, optimization, and improved structure performance have good use. [0003] However, during the construction of the mounting st...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
IPC IPC(8): E02D29/045
CPCE02D29/045
Inventor 禹丽峰王宁章新生耿大新程贤红黄永虎赵艳飞祝俊华王会谭成赵梓瑞夏杨张涛涛徐嘉龙刘成奇朱熊涛何元李越罗傅刚
Owner THE FIFTH ENG CO LTD OF CHINA TIESIJU CIVIL ENG GRP
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products