Looking for breakthrough ideas for innovation challenges? Try Patsnap Eureka!

Groove grabbing replacement filling obstacle clearing method before SMW construction method pile construction of boulder-containing stratum

A technology of construction method piles and large blocks, which is applied in excavation, sheet pile walls, foundation structure engineering, etc., can solve the problems that construction method piles cannot be directly constructed, the construction site is narrow, and there are landslides, etc., and achieve good operation results.

Pending Publication Date: 2021-10-01
ZHONGTIAN CONSTR GROUP
View PDF6 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0006] 1. It is necessary to design the position of the SMW construction method pile according to the detailed geological survey and supplementary survey report; if there are a large number of blocks with a diameter of more than 0.5m, the maximum particle size is 1.3m, and the depth of the block layer is distributed between 3.8m and 6m, and the construction method pile If there is a DN1500 waste rainwater pipe at the construction site, the construction method pile cannot be directly constructed;
[0007] 2. There is a risk of landslides if the conventional method of filling and clearing is adopted, and the construction site on site is narrow, and the straight-line distance between the construction method piles and the main road is only 2m, which does not meet the conditions for sloping and excavation

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Groove grabbing replacement filling obstacle clearing method before SMW construction method pile construction of boulder-containing stratum
  • Groove grabbing replacement filling obstacle clearing method before SMW construction method pile construction of boulder-containing stratum
  • Groove grabbing replacement filling obstacle clearing method before SMW construction method pile construction of boulder-containing stratum

Examples

Experimental program
Comparison scheme
Effect test

Embodiment

[0050] Please refer to Figure 1-Figure 4 , figure 1 It is a schematic flow diagram of the method in the embodiment of the present invention; figure 2 It is a working schematic diagram of the formation of the guide trench 1 in the embodiment of the present invention; image 3 It is a schematic diagram of the operation of the rotary drill to process rocks or abandoned pipelines in the embodiment of the present invention; Figure 4 It is a schematic diagram of the work of changing and filling the groove of the groove forming machine in the embodiment of the present invention.

[0051] The present embodiment provides the SMW engineering method pile construction method that contains large stone strata and grasps the groove and replaces and fills the obstacle removal method, and it comprises the following steps:

[0052] S1. Excavating and forming guide ditch 1 on the surface of the base layer along the preset trajectory position of the SMW construction method pile;

[0053] S...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

PropertyMeasurementUnit
Widthaaaaaaaaaa
Depthaaaaaaaaaa
Login to View More

Abstract

The invention provides a groove grabbing replacement filling obstacle clearing method before SMW construction method pile construction of a boulder-containing stratum, and relates to the technical field of groove grabbing replacement filling obstacle clearing. The method comprises the following steps that digging is conducted on the surface of a base layer along the preset track position where the SMW construction method pile needs to be implemented, and a guide ditch is formed; stone blocks or waste rainwater pipes in the soil layer below the guide ditch are crushed; groove grabbing and replacement filling treatment is carried out in the guide groove; and after replacement filling is completed, SMW construction method pile construction is prepared; By means of the method, large stones and waste rainwater pipes existing in the stratum are removed, the collapse risk is reduced, good operation conditions are provided for the SMW construction method, normal operation of the SMW construction method is guaranteed, and the good operation effect is achieved after the SMW construction method is completed; generally speaking, the construction mode is small in construction risk, high in safety and suitable for stratum obstacle removing construction when construction of the construction method piles is difficult due to the fact that the stratum contains unascertained large stones during construction of the SMW construction method piles.

Description

technical field [0001] The invention relates to the technical field of grasping groove replacement, filling and obstacle removal, in particular to a method for grasping groove replacement, filling and obstacle removal before construction of SMW construction method piles in strata containing large rocks. Background technique [0002] The SMW construction method is also known as the new cement-soil mixing pile wall, that is, inserting H-shaped steel (mostly H-shaped steel, but also Larsen type steel sheet piles, steel pipes, etc.) , making it a retaining wall of a supporting structure with both functions of force bearing and anti-seepage. [0003] The supporting features of the SMW support structure are: basically no noise during construction, little impact on the surrounding environment, and reliable structural strength. It can be used in any occasion where cement-soil mixing piles are suitable, especially suitable for clay and fine sand. Mainly soft ground; good water-retai...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
IPC IPC(8): E02D17/06E02D17/12E02D17/08E02F5/02E02F5/22E02F5/30E02D5/10E02D19/18
CPCE02D17/06E02D17/12E02D17/08E02F5/025E02F5/223E02F5/30E02D5/10E02D19/18
Inventor 陈锡阳马亮刘映晶卢敬科于建全冯超其张航
Owner ZHONGTIAN CONSTR GROUP
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Patsnap Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Patsnap Eureka Blog
Learn More
PatSnap group products