Sectional hoisting method
Patent Information
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- SHANGHAI WAIGAOQIAO SHIP BUILDING CO LTD
- Publication Date
- 2005-12-21
- Estimated Expiration
- Not applicable · inactive patent
Smart Images
Figure 1 Figure 2 Figure 3
Abstract
Description
technical field
[0001] The invention relates to a segmental hoisting process, in particular to a segmental hoisting process of a whole ship. Background technique
[0002] At present, the existing implementation schemes for the typical segmental turnover construction and overall segmental hoisting process of the gantry cranes built in modern docks are as follows: 600-ton gantry cranes are used for individual turnover and platform assembly during segmental hoisting. The disadvantages are: front and rear assembly A 600-ton gantry crane needs to be used three times for assembly and loading; after turning over in sections, because the top is heavy and the bottom is light, it is necessary to use straight braces to support and position the outer panels during the general assembly of the platform to prevent tipping, which is time-consuming and laborious.
[0003] When hoisting the superstructure, two hooks of the upper trolley are used for hoisting, and t...